| Year | Ministry | Recipient | Purpose | Contract Value | Paid This Year | Total Paid | Over Budget |
|---|---|---|---|---|---|---|---|
| 2014/2015 | Agriculture and Agri-Food | A&A Elevator Inc | Modernization of freight elevator, Ottawa, Ontario | $279,000 | $41,850 | $41,850 | - |
| 2014/2015 | Agriculture and Agri-Food | Besterd Mechanical | Cooling tower replacement, London, Ontario | $274,421 | $176,638 | $274,421 | - |
| 2014/2015 | Agriculture and Agri-Food | Can-Dive Construction Ltd | Rehabilitation of Highfield dam, Rush Lake, British Columbia | $615,999 | $41,250 | $41,250 | - |
| 2014/2015 | Agriculture and Agri-Food | City of Swift Current | Water distribution system, Swift Current, Saskatchewan | $1,010,333 | $952,381 | $952,381 | - |
| 2014/2015 | Agriculture and Agri-Food | Contracts under $250,000 and cost plus contracts under $25,000 (65 contractors) | Total | $0 | $2,631,146 | $0 | - |
| 2014/2015 | Agriculture and Agri-Food | Cornerstone Construction Ltd | Biocontainment laboratory upgrades, Morden, Manitoba | $1,142,790 | $0 | $1,142,790 | - |
| 2014/2015 | Agriculture and Agri-Food | Crane Structures Steel Ltd | New seed processing facility, Brandon, Manitoba | $2,250,239 | $355,516 | $2,250,239 | - |
| 2014/2015 | Agriculture and Agri-Food | Donald Servant Electric Limited | Installation of emergency generator, Ottawa, Ontario | $329,021 | $329,021 | $329,021 | - |
| 2014/2015 | Agriculture and Agri-Food | Graham Design Builders | New greenhouse and headerhouse, Morden, Manitoba | $8,331,768 | $1,325,908 | $8,161,685 | - |
| 2014/2015 | Agriculture and Agri-Food | Koncrete Construction Group | Rip-rap rehabilitation at Highfield dam, Rush Lake, Saskatchewan | $301,800 | $301,800 | $301,800 | - |
| 2014/2015 | Agriculture and Agri-Food | Kowal Constructions Alta Ltd | Headgate rehabilitation for Downie Lake dam, Maple Creek, Saskatchewan | $676,673 | $676,673 | $676,673 | - |
| 2014/2015 | Agriculture and Agri-Food | Les Contrôles AC Montréal Inc | Improvements to laboratory ventilation system, Québec, Quebec | $319,635 | $319,635 | $319,635 | - |
| 2014/2015 | Agriculture and Agri-Food | MH Stoneworks | Foundation waterproofing and verandah restoration for building 54, Ottawa, Ontario | $424,567 | $394,834 | $394,834 | - |
| 2014/2015 | Agriculture and Agri-Food | Michanie Construction Inc | Mobile compactor storage system for National Coleoptera Collection, Ottawa, Ontario | $280,891 | $45,005 | $45,005 | - |
| 2014/2015 | Agriculture and Agri-Food | Niacon Limited | New pesticide-free greenhouse addition, London, Ontario | $2,565,475 | $1,162,155 | $2,446,602 | - |
| 2014/2015 | Agriculture and Agri-Food | Raymond and Associates Roofing Inc | Roof replacement for building 22, Ottawa, Ontario | $308,795 | $107,500 | $107,500 | - |
| 2014/2015 | Agriculture and Agri-Food | Silver Ridge Construction | Agronomy building repairs and improvements, Lethbridge, Alberta | $965,140 | $716,243 | $716,243 | - |
| 2014/2015 | Canadian Heritage | Contracts under $250,000 and cost plus contracts under $25,000 (2 contractors) | Total | $0 | $105,923 | $0 | - |
| 2014/2015 | Canadian Heritage | Contracts under $250,000 and cost plus contracts under $25,000 (40 contractors) | Total | $0 | $862,462 | $0 | - |
| 2014/2015 | Canadian Heritage | Les Excavations Lafontaine Inc | Road maintenance, Québec, Quebec | $2,571,912 | $2,571,912 | $2,571,912 | - |
| 2014/2015 | Canadian Heritage | Plano Construction Inc | Conversion of the asset at 555 des Entreprises as a collection storage facility with a high density shelving system, Gatineau, Quebec | $18,255,919 | $0 | $12,367,294 | - |
| 2014/2015 | Canadian Heritage | SNC-Lavalin Inc | Conversion of the asset at 555 des Entreprises as a collection storage facility with a high density shelving system, Gatineau, Quebec | $634,285 | $1,522,406 | $634,285 | - |
| 2014/2015 | Canadian Heritage | SRL Construction | Conversion of the asset at 555 des Entreprises as a collection storage facility with a high density shelving system, Gatineau, Quebec | $785,946 | $0 | $342,481 | - |
| 2014/2015 | Canadian Heritage | Schoeler and Heaton Architects Inc | Conversion of the asset at 555 des Entreprises as a collection storage facility with a high density shelving system, Gatineau, Quebec | $827,540 | $0 | $800,772 | - |
| 2014/2015 | Environment | 9160-8794 Quebec Inc | Acquisition of 10 otentik tents, Wasagaming, Manitoba | $261,937 | $523,352 | $261,937 | - |
| 2014/2015 | Environment | 9160-8794 Quebec Inc | Acquisition of 12 otentik tents, Kouchibouguac National Park, New Brunswick | $288,591 | $288,591 | $288,591 | - |
| 2014/2015 | Environment | Associate Engineering Ltd | Replacement of a bridge, Hastings, Ontario | $718,318 | $306,702 | $433,451 | - |
| 2014/2015 | Environment | B&B Heavy Civil Construction Ltd | Rehabilitation of Icefield Parkway Bridges, Jasper National Park, Alberta | $723,582 | $0 | $0 | - |
| 2014/2015 | Environment | Bergevin Electrical Contracting Ltd | Paving and slope stabilisation of the Trans-Canada Highway, Glacier National Park, British Columbia | $7,653,830 | $5,300,012 | $5,300,012 | - |
| 2014/2015 | Environment | Brook Construction Inc | Rehabilitation of Deer Arm Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $818,000 | $13,938 | $13,938 | - |
| 2014/2015 | Environment | Buckland & Taylor Ltd | Rehabilitation of Woolsey Creek Bridge, Mount Revelstoke National Park, British Columbia | $285,640 | $285,640 | $285,640 | - |
| 2014/2015 | Environment | Carleton University | Repayment of capital lease obligation on leased research building, Ottawa, Ontario | $32,500,000 | $637,811 | $7,064,633 | - |
| 2014/2015 | Environment | Cimota Inc | Merrickville Swing Bridge repainting, Merrickville, Ontario | $443,770 | $377,450 | $377,450 | - |
| 2014/2015 | Environment | Contracts under $250,000 and cost plus contracts under $25,000 (21 contractors) | Total | $0 | $604,923 | $0 | - |
| 2014/2015 | Environment | Contracts under $250,000 and cost plus contracts under $25,000 (234 contractors) | Total | $0 | $15,878,529 | $0 | - |
| 2014/2015 | Environment | Copcan Contracting Ltd | Rehabilitation of the Illecillewaet Bridge number 3, Glacier National Park, British Columbia | $2,387,210 | $1,087,548 | $1,087,548 | - |
| 2014/2015 | Environment | DFS Inc | Carleton Martello Tower repairs, Saint John, New Brunswick | $301,807 | $110,631 | $301,807 | - |
| 2014/2015 | Environment | Dexter Construction Company Ltd | Halifax Citadel entrance redevelopment, Halifax, Nova Scotia | $444,845 | $309,740 | $309,740 | - |
| 2014/2015 | Environment | Dexter Construction Company Ltd | Parking lot upgrade, Halifax, Nova Scotia | $344,308 | $7,508 | $344,308 | - |
| 2014/2015 | Environment | Emil Anderson Construction Inc | Paving and slope stabilisation of Highway 16, Jasper National Park, Alberta | $3,427,641 | $6,064,826 | $3,427,641 | - |
| 2014/2015 | Environment | Excavation L Martel Inc | Replacement of lock gates 8, Chambly Canal, Quebec | $692,077 | $610,066 | $610,066 | - |
| 2014/2015 | Environment | Floyd's Construction Ltd | Rehabilitation of Baker's Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $899,200 | $899,095 | $899,095 | - |
| 2014/2015 | Environment | Floyd's Construction Ltd | Rehabilitation of Barter's Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $289,000 | $289,000 | $289,000 | - |
| 2014/2015 | Environment | Floyd's Construction Ltd | Rehabilitation of Bottom Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $483,600 | $145,098 | $170,097 | - |
| 2014/2015 | Environment | Floyd's Construction Ltd | Rehabilitation of Mill Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $336,600 | $40,033 | $65,033 | - |
| 2014/2015 | Environment | Floyd's Construction Ltd | Rehabilitation of Rocky Barachois Bridge, Gros Morne National Park, Newfoundland and Labrador | $496,237 | $466,542 | $496,237 | - |
| 2014/2015 | Environment | Guenthers Landscaping Ltd | Repair of the Banff Legacy Trail, Banff National Park, Alberta | $1,544,455 | $1,544,455 | $1,544,455 | - |
| 2014/2015 | Environment | H R Doornekamp Construction Ltd | Rehabilitation of Healey Falls Lock 15, Campbellford, Ontario | $2,002,483 | $802,089 | $1,863,990 | - |
| 2014/2015 | Environment | HRC Construction Inc | Rehabilitation of Woolsey Creek Bridge, Mount Revelstoke National Park, British Columbia | $2,391,650 | $1,659,105 | $1,659,105 | - |
| 2014/2015 | Environment | Harbourside Engineering Consultants | Design work for the replacement of the Northwest River Bridge, Glovertown, Newfoundland and Labrador | $667,158 | $630,158 | $667,158 | - |
| 2014/2015 | Environment | Harvey Jocelyn Entrepreneur Inc | Rehabilitation of the wastewater treatment facilities, Baie-Sainte-Catherine, Quebec | $322,128 | $322,128 | $322,128 | - |
| 2014/2015 | Environment | Horseshoe Hill Construction Inc | Big Brook Bridge repairs, Glovertown, Newfoundland and Labrador | $2,681,391 | $2,578,384 | $2,681,384 | - |
| 2014/2015 | Environment | Horseshoe Hill Construction Inc | Replacement of Shoal Cove Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $2,779,012 | $34,011 | $34,011 | - |
| 2014/2015 | Environment | Innovative Civil Contractors Inc | Rehabilitation of Dick's Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $1,264,019 | $47,675 | $47,675 | - |
| 2014/2015 | Environment | Innovative Civil Contractors Inc | Rehabilitation of East Branch Bridge, Gros Morne National Park, Newfoundland and Labrador | $680,050 | $79,430 | $79,430 | - |
| 2014/2015 | Environment | Innovative Civil Contractors Inc | Rehabilitation of Southeast Brook Bridge, Gros Morne National Park, Newfoundland and Labrador | $619,776 | $76,740 | $76,740 | - |
| 2014/2015 | Environment | Innovative Civil Contractors Inc | Rehabilitation of an overpass, Glacier National Park, British Columbia | $3,198,866 | $2,663,068 | $2,860,315 | - |
| 2014/2015 | Environment | Innovative Civil Contractors Inc | Rehabilitation of the Illecillewaet Bridge number 1, Glacier National Park, British Columbia | $2,756,000 | $0 | $0 | - |
| 2014/2015 | Environment | Innovative Civil Contractors Inc | Rehabilitation of the Illecillewaet Bridge number 2, Glacier National Park, British Columbia | $2,796,000 | $0 | $0 | - |
| 2014/2015 | Environment | Interoute Construction Ltd | Paving and slope stabilisation of the Trans-Canada Highway, Glacier National Park, British Columbia | $1,557,909 | $1,557,909 | $1,557,909 | - |
| 2014/2015 | Environment | Interoute Construction Ltd | Paving and slope stabilisation of the Trans-Canada Highway, Mount Revelstoke National Park, British Columbia | $3,907,950 | $7,025,550 | $3,907,950 | - |
| 2014/2015 | Environment | Ironclad Earthworks Ltd | Repair of the Cascade Valley Trails, Banff National Park, Alberta | $1,441,694 | $963,791 | $963,791 | - |
| 2014/2015 | Environment | Island West Coast Developments Ltd | Electrification of Green Point campground, Ucluelet, British Columbia | $1,215,931 | $1,215,931 | $1,215,931 | - |
| 2014/2015 | Environment | Island West Coast Developments Ltd | Sewer and water system, Pacific Rim, British Columbia | $3,819,145 | $40,086 | $3,819,145 | - |
| 2014/2015 | Environment | J-1 Contracting Ltd | Reconstruction of Eastport Road, Glovertown, Newfoundland and Labrador | $3,579,999 | $1,456,717 | $1,456,717 | - |
| 2014/2015 | Environment | J-1 Contracting Ltd | Repaving of Highway 430, Gros Morne National Park, Newfoundland and Labrador | $6,730,997 | $2,360,144 | $2,386,106 | - |
| 2014/2015 | Environment | J-1 Contracting Ltd | Repaving of the Trans-Canada Highway and culvert installation, Glovertown, Newfoundland and Labrador | $10,464,799 | $1,568,685 | $10,464,799 | - |
| 2014/2015 | Environment | J-1 Contracting Ltd | Resurfacing of Highway 431, Gros Morne National Park, Newfoundland and Labrador | $7,500,000 | $214,329 | $214,329 | - |
| 2014/2015 | Environment | K2 Design Build Inc | Construction of a 4 season multi-use facility, Niagara Falls, Ontario | $1,264,085 | $793,737 | $1,250,909 | - |
| 2014/2015 | Environment | Kluane Community Development Corporation | Slims River Road upgrade, Kluane National Park, Yukon | $250,015 | $250,000 | $250,000 | - |
| 2014/2015 | Environment | LVM Inc | Rehabilitation of the Otonabee Dam at Lock 23, Peterborough, Ontario | $282,184 | $241,078 | $241,078 | - |
| 2014/2015 | Environment | Livewire Electric Ltd | Electrical expansion in Beaver Glen campground, Prince Albert National Park, Saskatchewan | $348,880 | $260,982 | $260,982 | - |
| 2014/2015 | Environment | Louis W Bray Construction Ltd | Rehabiliation of the Poonamlie Dam, Smiths Falls, Ontario | $2,776,630 | $824,868 | $824,868 | - |
| 2014/2015 | Environment | Maritime Fence Ltd | Paving and slope stabilisation, Yoho National Park, British Columbia | $2,071,674 | $2,071,674 | $2,071,674 | - |
| 2014/2015 | Environment | McElhanney Consulting Services Ltd | Avalanche mitigation, Various locations, British Columbia | $380,951 | $380,951 | $380,951 | - |
| 2014/2015 | Environment | McElhanney Consulting Services Ltd | Design of wildlife fencing and crossing structures, Kootenay National Park, British Columbia | $285,391 | $285,391 | $285,391 | - |
| 2014/2015 | Environment | McElhanney Consulting Services Ltd | Paving and slope stabilisation of Highway 16, Jasper National Park, Alberta | $321,714 | $321,714 | $321,714 | - |
| 2014/2015 | Environment | McElhanney Consulting Services Ltd | Paving and slope stabilisation of the Trans-Canada Highway, Glacier National Park, British Columbia | $379,080 | $379,080 | $379,080 | - |
| 2014/2015 | Environment | McElhanney Consulting Services Ltd | Paving and slope stabilisation, Yoho National Park, British Columbia | $297,983 | $297,983 | $297,983 | - |
| 2014/2015 | Environment | McElhanney Consulting Services Ltd | Preliminary design for rehabilitation of the Trans-Canada Highway, Various locations, British Columbia | $297,632 | $297,632 | $297,632 | - |
| 2014/2015 | Environment | Melville Trucking & Excavating Ltd | Realignment of Highway 430, Gros Morne National Park, Newfoundland and Labrador | $4,053,828 | $2,380,126 | $2,797,954 | - |
| 2014/2015 | Environment | Metric Contracting Services Corp | Reconstruction of the Bolsover Dam at Lock 37, Bolsover, Ontario | $21,778,237 | $6,080,594 | $12,124,356 | - |
| 2014/2015 | Environment | Mountain Rock Stabilization Services Inc | Paving and slope stabilisation, Yoho National Park, British Columbia | $421,652 | $421,652 | $421,652 | - |
| 2014/2015 | Environment | Nappaq Design and Construction Ltd | Construction of a cabin, Tuktut Nogait National Park, Northwest Territories | $327,375 | $327,375 | $327,375 | - |
| 2014/2015 | Environment | Okanagan Aggregates Ltd | Paving and slope stabilisation, Yoho National Park, British Columbia | $3,083,222 | $3,083,222 | $3,083,222 | - |
| 2014/2015 | Environment | Okanagan Aggregates Ltd | Paving of Highway 93, Various locations, Alberta | $2,237,407 | $2,237,407 | $2,237,407 | - |
| 2014/2015 | Environment | Okanagan Aggregates Ltd | Rehabilitation of roads, Various locations, Alberta | $9,652,900 | $1,200,000 | $1,200,000 | - |
| 2014/2015 | Environment | Okanagan Aggregates Ltd | Repair of the Minnewanka culvert and Banff Legacy Trail Bridge, Banff National Park, Alberta | $932,988 | $802,836 | $802,836 | - |
| 2014/2015 | Environment | Paulco Ltd | Repair of the Spray River Trail, Banff National Park, Alberta | $806,380 | $717,977 | $717,977 | - |
| 2014/2015 | Environment | Peter's Bros Construction Ltd | Paving and slope stabilisation of the Trans-Canada Highway, Banff National Park, Alberta | $2,278,143 | $2,278,143 | $2,278,143 | - |
| 2014/2015 | Environment | Pranger-Debruyn Construction Ltd | Rehabilitation of the Ottawa Locks washrooms, Ottawa, Ontario | $352,951 | $251,951 | $352,951 | - |
| 2014/2015 | Environment | Rob Smith & Son Backhoe & Trucking Ltd | Connection to the municipal water and wastewater systems, Wasagaming, Manitoba | $1,709,050 | $359,200 | $1,709,050 | - |
| 2014/2015 | Environment | SDI Builders Ltd | Upgrade of the road and entranceway of Bruce Peninsula National Park, Tobermory, Ontario | $361,421 | $361,421 | $361,421 | - |
| 2014/2015 | Environment | St Isidore Asphalte Ltd | Reconstruction of Highway 114, Fundy National Park, New Brunswick | $5,912,340 | $2,364,655 | $2,364,655 | - |
| 2014/2015 | Environment | Stantec Consulting Ltd | Rehabilitation of a bridge, Chambly Canal, Quebec | $375,550 | $222,000 | $222,000 | - |
| 2014/2015 | Environment | Stephen P Kylie | Purchase of land and house at Lock 19, Peterborough, Ontario | $285,088 | $285,088 | $285,088 | - |
| 2014/2015 | Environment | Windley Contracting Ltd | Construction of washroom facilities at Green Point Campground, Ucluelet, British Columbia | $1,757,727 | $1,600,943 | $1,600,943 | - |
| 2014/2015 | Finance | Bentall Kennedy | Leasehold improvements - FAC013 Toronto 15th Phase 2, Toronto, Ontario | $1,533,000 | $52,071 | $52,071 | - |
| 2014/2015 | Finance | Contracts under $250,000 and cost plus contracts of less than $25,000 (5 contractors) | Total | $417,119 | $413,901 | $413,901 | - |
| 2014/2015 | Finance | Public Works and Government Services Canada | Leasehold Improvements - 90 Elgin, Ottawa, Ontario | $2,100,634 | $2,099,894 | $2,099,894 | - |
| 2014/2015 | Finance | Shared Services Canada | Leasehold improvements - 90 Elgin, Ottawa, Ontario | $2,654,955 | $1,397,852 | $2,654,955 | - |
| 2014/2015 | Fisheries and Oceans | B & R Enterprises Limited | Wharf construction, Brig Bay, Newfoundland and Labrador | $986,905 | $441,168 | $942,168 | - |
| 2014/2015 | Fisheries and Oceans | B & R Enterprises Limited | Wharf construction, Mary's Harbour, Newfoundland and Labrador | $2,200,440 | $550,015 | $2,200,440 | - |
| 2014/2015 | Fisheries and Oceans | Bennett's Construction | Wharf reconstruction, Burin, Newfoundland and Labrador | $384,183 | $134,183 | $384,183 | - |
| 2014/2015 | Fisheries and Oceans | Budgell's Equipment & Rentals Limited | Breakwater reconstruction, Cow Head, Newfoundland and Labrador | $766,949 | $766,949 | $766,949 | - |
| 2014/2015 | Fisheries and Oceans | Coady Construction & Excavating Ltd | Marginal wharf construction, Fermeuse, Newfoundland and Labrador | $2,598,437 | $1,334,937 | $2,598,437 | - |
| 2014/2015 | Fisheries and Oceans | Contracts under $250,000 and cost plus contracts under $25,000 (120 contractors) | Total | $0 | $5,547,244 | $0 | - |
| 2014/2015 | Fisheries and Oceans | Floyd's Construction Ltd | Wharf extension, Twillingate, Newfoundland and Labrador | $644,939 | $644,939 | $644,939 | - |
| 2014/2015 | Fisheries and Oceans | Floyd's Construction Ltd | Wharf reconstruction, Bartlett's Harbour, Newfoundland and Labrador | $1,862,200 | $652,200 | $652,200 | - |
| 2014/2015 | Fisheries and Oceans | GMM Const Inc | Wharf reconstruction, Moose Lake, Manitoba | $285,656 | $285,656 | $285,656 | - |
| 2014/2015 | Fisheries and Oceans | Glenko Enterprises (1994) Ltd | Breakwater reconstruction, Pine dock, Manitoba | $398,560 | $354,108 | $354,108 | - |
| 2014/2015 | Fisheries and Oceans | Huron District Contracting Limited | Breakwater reconstruction, South Bruce Peninsula, Ontario | $663,238 | $663,238 | $663,238 | - |
| 2014/2015 | Fisheries and Oceans | J & E Enterprises Ltd | Harbour development, Harbour Breton, Newfoundland and Labrador | $1,306,700 | $1,305,048 | $1,305,048 | - |
| 2014/2015 | Fisheries and Oceans | J & E Enterprises Ltd | Wharf deck reconstruction, Hermitage-Sandyville, Newfoundland and Labrador | $270,912 | $199,200 | $270,912 | - |
| 2014/2015 | Fisheries and Oceans | J & E Enterprises Ltd | Wharf reconstruction, Norman's Cove-Long Cove, Newfoundland and Labrador | $1,393,066 | $854,266 | $1,393,066 | - |
| 2014/2015 | Fisheries and Oceans | Newfound Construction Ltd | Finger pier extension, Harbour Grace, Newfoundland and Labrador | $1,641,925 | $758,947 | $758,947 | - |
| 2014/2015 | Fisheries and Oceans | Pittmans Enterprises Limited | Breakwater reconstruction, Blue Beach, Newfoundland and Labrador | $506,461 | $506,461 | $506,461 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Breakwater reconstruction, St Bride's, Newfoundland and Labrador | $1,857,352 | $1,307,517 | $1,307,517 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Harbour development, Arnold's Cove, Newfoundland and Labrador | $1,538,809 | $1,538,809 | $1,538,809 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Harbour development, Old Perlican, Newfoundland and Labrador | $331,276 | $114,976 | $331,276 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Wharf construction, Riverhead, Newfoundland and Labrador | $632,889 | $632,889 | $632,889 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Wharf extension, Mary's Harbour, Newfoundland and Labrador | $2,012,047 | $447,047 | $447,047 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Wharf reconstruction, Arnold's Cove, Newfoundland and Labrador | $2,255,745 | $621,745 | $2,255,745 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Wharf reconstruction, Jerseyside, Newfoundland and Labrador | $908,596 | $478,600 | $478,600 | - |
| 2014/2015 | Fisheries and Oceans | R J G Construction Ltd | Wharf reconstruction, Ramea, Newfoundland and Labrador | $1,646,544 | $1,146,544 | $1,146,544 | - |
| 2014/2015 | Fisheries and Oceans | Rocktel Inc | Replacement of the marine communications and traffic services tower, Notre-Dame-du-Portage, Quebec | $316,503 | $214,641 | $214,641 | - |
| 2014/2015 | Fisheries and Oceans | Terry Lavallee Construction | Wharf construction, Berens River, Manitoba | $270,350 | $270,350 | $270,350 | - |
| 2014/2015 | Fisheries and Oceans | Terry Lavallee Construction | Wharf reconstruction, Easterville, Manitoba | $360,963 | $360,963 | $360,963 | - |
| 2014/2015 | Fisheries and Oceans | Trident Construction Limited | Harbour development, Port de Grave, Newfoundland and Labrador | $748,250 | $411,229 | $748,250 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Aktor SA | Chancery fit-up, Athens, Greece | $3,141,168 | $2,942,595 | $2,942,595 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Black and McDonald Ltd | Chancery gatehouse reconfiguration, New Delhi, India | $2,809,165 | $2,251,455 | $2,465,117 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Black and McDonald Ltd | Electrical upgrades chancery and staff quarter, Islamabad, Pakistan | $3,172,290 | $0 | $3,069,378 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Brigade Enterprises Ltd | Fit-up of consulate office, Bangalore, India | $2,311,135 | $176,553 | $1,831,814 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | CPM Projects | Fit-up of chancery, Abuja, Nigeria | $507,779 | $394,076 | $394,076 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Cannonbye Construction Ltd | Installation of prime power generating system for the compound, Port-au-Prince, Haiti | $723,452 | $0 | $714,516 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Casais Brasil Empreedimentos Lda | Expansion and fit-up of consulate, Rio de Janeiro, Brazil | $2,890,369 | $1,030,601 | $2,830,466 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Casais Engenharia E Construcaio SA | Chancery construction, Rabat, Morocco | $14,096,660 | $722,971 | $14,096,660 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Charles Russell | Purchase of staff quarters, London, United Kingdom | $3,078,608 | $3,363,244 | $3,078,608 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Cit Blaton | Fit-up of the new chancery, Brussels, Belgium | $4,749,528 | $946,708 | $1,050,748 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Clarke and Associates Construction Inc | Construction of office space annex, Bridgetown, Barbados | $1,455,741 | $1,087,018 | $1,439,317 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | ComNet | Cable supply installation and testing, Amman, Jordan | $251,000 | $0 | $242,175 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | ComNet | Cable supply installation and testing, Hong Kong, China | $490,068 | $394,579 | $490,067 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Construction Outfitters International | Design build and fit-up of the chancery, Damascus, Syria | $6,349,317 | $0 | $3,261,795 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Contracts under $250,000 and cost plus contracts under $25,000 (153 contractors) | Total | $0 | $2,325,822 | $0 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Corporation Ukrzhylbud | Fit-up of chancery, Kiev, Ukraine | $3,730,332 | $112,070 | $3,647,253 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Durabond | Official residence electrical upgrade, Havana, Cuba | $354,888 | $0 | $245,858 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Edwin Patricio Mora Guzman | Expansion of chancery, Quito, Ecuador | $684,150 | $510,766 | $602,983 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Groupe Villemain Ile de France | Renovation of the official residence, Paris, France | $545,951 | $523,828 | $523,828 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | ISG Olson CISC | Chancery upgrade, Moscow, Russia | $551,401 | $0 | $0 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Interamericas World Center S A | Purchase of chancery, Guatemala City, Guatemala | $3,422,580 | $0 | $3,422,580 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Kent Construction Limited | Chancery upgrade, Bridgetown, Barbados | $3,444,284 | $1,984,089 | $3,263,901 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | LP Holding Co Ltd | Fit-up of office space, Yangon, Myanmar | $605,312 | $185,508 | $605,312 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Louis EL Hachem Engineering and Contracting SARL | Chancery retrofit, Beirut, Lebanon | $7,500,819 | $2,094,446 | $6,501,653 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | M and W Tech Projects | Construction of perimeter wall around compound site, Kabul, Afganistan | $3,557,728 | $335,973 | $3,557,728 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Mandhir Construction | Chancery upgrade, Nairobi, Kenya | $3,098,760 | $3,044,120 | $3,044,120 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Marcomm Inc | Cable supply installation and testing, London, United Kingdom | $2,095,428 | $1,885,885 | $1,885,885 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Modern Interiors | Fit-up of chancery, Cairo, Egypt | $1,139,302 | $1,139,302 | $1,139,302 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Nahman Construction | Construction of new chancery, Abuja, Nigeria | $10,387,021 | $2,916,982 | $8,860,105 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Nile City Investments | Fit-up of chancery space, Cairo, Egypt | $2,468,601 | $1,220,589 | $1,220,589 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Nile City Investments | Purchase of chancery, Cairo, Egypt | $9,870,706 | $0 | $9,680,706 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Overbury | Canada House chancery renovation, London, United Kingdom | $80,457,240 | $80,340,822 | $80,447,240 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | PMB Electrical | Specialty fit-up of office space, Nairobi, Kenya | $308,000 | $201,728 | $201,728 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | PMB Electrical | Specialty fit-up of office space, Rabat, Morocco | $322,430 | $312,837 | $312,837 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | PMCA Interior Architectural Construction Consultancy Shanghai Ltd | Design construction relocation of consulate general of Canada, Guangzhou, China | $1,754,953 | $0 | $0 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Parkeray Limited | Fit-up of office space, London, United Kingdom | $6,486,558 | $0 | $5,208,227 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Parkeray Limited | Official residence design and construction, London, United Kingdom | $3,677,839 | $3,490,190 | $3,490,190 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Pat Davie Ltd | Design build fit-up new office space for Quebec Immigration Office, Hong Kong, China | $3,044,277 | $680,137 | $2,935,547 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Pat Davie Ltd | Design build fit-up new office space for relocation of central operation of Consulate General, Hong Kong, China | $2,537,147 | $211,591 | $2,500,044 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Pat Davie Ltd | Design build fit-up new office space for relocation of regular operations of Consulate General, Hong Kong, China | $5,566,053 | $920,620 | $5,566,009 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Perfect Company Contractors | Chancery upgrade, Cairo, Egypt | $976,213 | $145,002 | $921,305 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Rio Douro Construction A | Upgrade chancery guardhouse screening area and sally ports, Harare, Zimbabwe | $756,526 | $0 | $661,891 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | SRL Construction | Design build fit-up of chancery, Yaoundé, Cameroon | $2,725,173 | $1,416,752 | $2,715,893 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Samra Enterprises | Seismic upgrade chancery and staff quarters, Islamabad, Pakistan | $2,822,503 | $275,293 | $2,820,023 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Saraya Albinaa Contracting | Chancery modernization expansion fit-up landscaping and swing space, Riyadh, Saudi Arabia | $10,837,185 | $4,208,000 | $4,208,000 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Sarl Groupe Sept Entreprise | Construction of new guard house sally port and entrance chancery, Algiers, Algeria | $1,901,542 | $1,532,811 | $1,900,000 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Terrain Services Company ss Ltd | Design construct office space, Juba, South Sudan | $583,394 | $583,394 | $583,394 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Vita Construction Limited | Chancery upgrade, Lagos, Nigeria | $685,011 | $349,618 | $384,971 | - |
| 2014/2015 | Foreign Affairs, Trade and Development | Wajih Contracting | Construction of new chancery, Amman, Jordan | $10,075,513 | $18,169 | $9,611,074 | - |
| 2014/2015 | Health | Architecture49 Inc | Construction Design Banting Building, Ottawa, Ontario | $1,941,454 | $333,176 | $1,860,830 | - |
| 2014/2015 | Health | Architecture49 Inc | JC Wilt Infectious Disease Centre, Winnipeg, Manitoba | $4,745,994 | $55,838 | $4,720,276 | - |
| 2014/2015 | Health | Contracts under $250,000 and cost plus contracts of less than $25,000 (6 contractors) | Total | $0 | $569,162 | $0 | - |
| 2014/2015 | Health | Contracts under $250,000 and cost plus contracts under $25,000 (1 Contractor) | Total | $0 | $75,126 | $0 | - |
| 2014/2015 | Health | Contracts under $250,000 and cost plus contracts under $25,000 (6 contractors) | Total | $0 | $331,233 | $0 | - |
| 2014/2015 | Health | McDonald Brothers Construction Inc | Construction Design Banting Building, Ottawa, Ontario | $17,690,253 | $10,552,001 | $10,829,001 | - |
| 2014/2015 | Health | PCL Constructors Canada Inc | JC Wilt Infectious Disease Centre, Winnipeg, Manitoba | $26,318,102 | $396,633 | $26,318,102 | - |
| 2014/2015 | Indian Affairs and Northern Development | Contracts under $250,000 and cost plus contracts under $25,000 (20 contractors) | Total | $0 | $630,452 | $0 | - |
| 2014/2015 | Indian Affairs and Northern Development | EllisDon Corporation | Building Construction - Canadian High Arctic Research Station, Cambridge Bay, Nunavut | $102,623,133 | $25,806,241 | $25,806,241 | - |
| 2014/2015 | Industry | 168063 Canada Inc | Electrical system upgrade, Ottawa, Ontario | $3,615,884 | $2,081,610 | $3,464,010 | - |
| 2014/2015 | Industry | AMD Holdings Ltd | Roofing replacement phase I, St-John's, Newfoundland and Labrador | $482,000 | $20,980 | $482,000 | - |
| 2014/2015 | Industry | Black & MacDonald Ltd | Replacement of the chiller and heat rejection system, Saskatoon, Saskatchewan | $1,028,980 | $368,954 | $1,028,980 | - |
| 2014/2015 | Industry | Coco Paving Inc | U-61 Road reconstruction, Ottawa, Ontario | $400,863 | $400,863 | $400,863 | - |
| 2014/2015 | Industry | Contracts under $250,000 and cost plus contracts of less than $25,000 (118 contractors) | Total | $0 | $8,301,177 | $0 | - |
| 2014/2015 | Industry | Contracts under $250,000 and cost plus contracts under $25,000 (1 contractor) | Total | $0 | $61,797 | $0 | - |
| 2014/2015 | Industry | Dalcon Enterprises Inc | M-49 Synthetic fuels facility, Ottawa, Ontario | $811,934 | $36,388 | $732,834 | - |
| 2014/2015 | Industry | Drycore Electric 2002 Inc | M-32 Electrical room upgrade, Ottawa, Ontario | $823,427 | $373,335 | $823,427 | - |
| 2014/2015 | Industry | Flynn Canada | Roof replacement phase III, St-John's, Newfoundland and Labrador | $714,300 | $684,822 | $684,822 | - |
| 2014/2015 | Industry | Konecranes Canada | U-70 Crane replacement, Ottawa, Ontario | $262,545 | $133,048 | $133,048 | - |
| 2014/2015 | Industry | McNolty Mechanical | M-6 Piping replacement, Ottawa, Ontario | $562,514 | $562,514 | $562,514 | - |
| 2014/2015 | Industry | Morin Insulation and Roofing | M-55 Main elevator modernization, Ottawa, Ontario | $313,630 | $313,630 | $313,630 | - |
| 2014/2015 | Industry | Polyval Construction Inc | Bathroom renovation, Boucherville, Quebec | $260,900 | $110,371 | $110,371 | - |
| 2014/2015 | Industry | Regina Elevator Co Ltd | Elevator replacement, Saskatoon, Saskatchewan | $335,675 | $0 | $0 | - |
| 2014/2015 | Industry | SK Sheet Metal Ltd | M-10 Electrical Room Ventilation, Ottawa, Ontario | $269,711 | $269,711 | $269,711 | - |
| 2014/2015 | Industry | Serge Zimola Construction Inc | M-50 Laboratory construction, Ottawa, Ontario | $1,155,869 | $942,087 | $1,155,869 | - |
| 2014/2015 | Industry | TP Crawford Ltd | S-77 Nanolab fume exhaust system, Ottawa, Ontario | $673,727 | $673,727 | $673,727 | - |
| 2014/2015 | Industry | Thompson Boiler Works | M-10 Chiller replacement, Ottawa, Ontario | $276,900 | $33,800 | $33,800 | - |
| 2014/2015 | Industry | Waterdon Construction Ltd | M-23A Nanolabs renovation, Ottawa, Ontario | $331,000 | $115,850 | $115,850 | - |
| 2014/2015 | Justice | Bassi Construction Ltd | Leasehold improvement 90 Sparks Street, Ottawa, Ontario | $454,502 | $248,061 | $248,061 | - |
| 2014/2015 | Justice | Contracts under $250,000 and cost plus contracts of less than $25,000 (1 contractor) | Total | $0 | $2,032 | $0 | - |
| 2014/2015 | Justice | Contracts under $250,000 and cost plus contracts under $25,000 (3 contractors) | Total | $0 | $154,120 | $0 | - |
| 2014/2015 | National Defence | 2086370 Ontario Inc | CFHA Minor Recap M & UU Style residential housing units, Kingston, Ontario | $529,976 | $514,976 | $514,976 | - |
| 2014/2015 | National Defence | 2086370 Ontario Inc | CFHA Recap N Style, Kingston, Ontario | $257,692 | $257,692 | $257,692 | - |
| 2014/2015 | National Defence | 2347962 Ontario Inc o/a Kent Construction | Renovate kitchens in houses/ duplexes/ quads/ and apartments, Petawawa, Ontario | $609,972 | $609,972 | $609,972 | - |
| 2014/2015 | National Defence | 2852-6648 Quebec Inc Excavation L M R | Recap Main Wharf HMCS Champ Chicoutimi Naval Reserve, Bagotville, Quebec | $431,847 | $372,534 | $372,534 | - |
| 2014/2015 | National Defence | 44980 Nfld Inc | Install New GRA Perimeter Fence, Happy Valley-Goose Bay, Newfoundland and Labrador | $518,000 | $209,875 | $518,000 | - |
| 2014/2015 | National Defence | 9215-1083 Québec Inc / Entreprise Étoile | Funded Standing offer agreement - Painting Contractor, Montréal, Quebec | $669,545 | $109,035 | $286,522 | - |
| 2014/2015 | National Defence | 9250 - 3150 Quebec Inc | Renovate kitchens in row houses, Petawawa, Ontario | $453,360 | $453,360 | $453,360 | - |
| 2014/2015 | National Defence | 9250 - 3150 Quebec Inc | Rewire and Re-Insulation on residential housing units, Petawawa, Ontario | $951,700 | $951,700 | $951,700 | - |
| 2014/2015 | National Defence | 9271-3247 Quebec Inc | Leasehold improvements of taxes services office, Québec, Quebec | $445,000 | $38,703 | $38,703 | - |
| 2014/2015 | National Defence | A & J Hanna Construction Ltd | Recap six residential units, Gagetown, New Brunswick | $629,340 | $629,340 | $629,340 | - |
| 2014/2015 | National Defence | A Fresh Look Painting and Decorating | Kitchen Renovations, Winnipeg, Manitoba | $516,000 | $160,020 | $160,020 | - |
| 2014/2015 | National Defence | A Plante et Freres Inc | Recap roofs B216, Saguenay, Quebec | $363,424 | $363,424 | $363,424 | - |
| 2014/2015 | National Defence | AA Sturgeon Construction Ltd | McGregor Armoury - Repair Weeping Tile Waterproofing and Site Drainage, Winnipeg, Manitoba | $572,378 | $11,868 | $572,378 | - |
| 2014/2015 | National Defence | AGC and Associates Inc | Expand JRCC Alternate Site, Quinte West, Ontario | $582,175 | $21,952 | $582,175 | - |
| 2014/2015 | National Defence | AGC and Associates Inc | R23 - Replace Windows, Kingston, Ontario | $548,142 | $0 | $548,142 | - |
| 2014/2015 | National Defence | ARMAG Corporation | Purchase/Install Portable Weapons Lockup, Gagetown, New Brunswick | $336,258 | $336,258 | $336,258 | - |
| 2014/2015 | National Defence | ASCO Construction Ltd | Training accommodation facility, Petawawa, Ontario | $12,029,425 | $6,686 | $12,029,425 | - |
| 2014/2015 | National Defence | AWD Contractors | Reskin QRA Shelters 1 2 and 3, Quinte West, Ontario | $304,439 | $304,439 | $304,439 | - |
| 2014/2015 | National Defence | Access Contracting Limited | Greenwood - Recap - 3 residential housing units, Greenwood, Nova Scotia | $256,629 | $251,629 | $251,629 | - |
| 2014/2015 | National Defence | Access Contracting Limited | Upgrade mods at Neptune House B164, Greenwood, Nova Scotia | $575,575 | $528,540 | $528,540 | - |
| 2014/2015 | National Defence | Al Bruch's Carpentry Ltd | Kitchen Renovations for residential housing units, Victoria, British Columbia | $328,193 | $328,193 | $328,193 | - |
| 2014/2015 | National Defence | Al Bruch's Carpentry Ltd | Standing offer agreement - General construction, Esquimalt, British Columbia | $3,596,674 | $0 | $3,596,674 | - |
| 2014/2015 | National Defence | Albiani Construction Ltd | Building 63 - Air Conditioning PTAC Systems, Winnipeg, Manitoba | $617,158 | $563,478 | $607,358 | - |
| 2014/2015 | National Defence | Alex Ouellet Inc | Standing offer agreement - Electrical Contractor - Valcartier, Courcelette, Quebec | $163,257 | $23,436 | $163,257 | - |
| 2014/2015 | National Defence | Allen Mechanical Inc | R32 Renos to kitchen servery/ back-up power/ back-up water Yeo Hall, Kingston, Ontario | $722,008 | $713,208 | $713,208 | - |
| 2014/2015 | National Defence | Allen Mechanical Inc | Yeo Hall air conditioner retrofit for Kitchen/Dental Leakage Problem, Kingston, Ontario | $399,710 | $362,914 | $362,914 | - |
| 2014/2015 | National Defence | Alliance Energy Limited | Hangar 6 & 7 Lighting Upgrade, Moose Jaw, Saskatchewan | $285,900 | $204,952 | $204,952 | - |
| 2014/2015 | National Defence | Almiq Contracting Ltd | Nanisivik Construction and Consulting Services, Nanisivik, Nunavut | $55,857,000 | $9,994,443 | $9,994,443 | - |
| 2014/2015 | National Defence | Amec Construction Inc | Reconfigure Building 117, Saguenay, Quebec | $263,083 | $41,406 | $263,083 | - |
| 2014/2015 | National Defence | Amron Construction | Batus General Construction, Suffield, Alberta | $348,423 | $0 | $348,423 | - |
| 2014/2015 | National Defence | Amron Construction | Combustion Laboratory, Suffield, Alberta | $5,148,081 | $2,182,877 | $5,148,081 | - |
| 2014/2015 | National Defence | Amron Construction | Repair Site and Roof Drainage Vimy Armoury, Lethbridge, Alberta | $666,661 | $4,500 | $666,661 | - |
| 2014/2015 | National Defence | Amron Construction | Standing offer agreement - General Construction - Batus, Suffield, Alberta | $289,285 | $0 | $289,285 | - |
| 2014/2015 | National Defence | Amron Construction | Standing offer agreement - General construction - DRDC, Suffield, Alberta | $442,564 | $0 | $442,564 | - |
| 2014/2015 | National Defence | Amron Construction | Standing offer agreement - General construction, Suffield, Alberta | $315,462 | $0 | $315,462 | - |
| 2014/2015 | National Defence | Anglin Group Ltd | Construction Modifications Health Services Centre, Kingston, Ontario | $286,130 | $160,511 | $160,511 | - |
| 2014/2015 | National Defence | Aquicon Construction Company Ltd | All Ranks Dining Facility # 2 Vickers-North Kitchen, Borden, Ontario | $17,767,219 | $11,341,233 | $16,043,375 | - |
| 2014/2015 | National Defence | Ardec Construction Inc | Install emergency exits Cathcart Armoury, Montréal, Quebec | $632,304 | $177,832 | $632,304 | - |
| 2014/2015 | National Defence | Argue Construction Ltd | Upgrade Heavy Vehicle Maintenance Pit at building BB-102, Petawawa, Ontario | $563,801 | $563,801 | $563,801 | - |
| 2014/2015 | National Defence | Arnil Construction Ltd | Recap 4 Type K KK residential housing units, Moose Jaw, Saskatchewan | $863,258 | $846,458 | $846,458 | - |
| 2014/2015 | National Defence | Atlantic Industrial Services | D2/D5 retaining wall Replacement, Halifax, Nova Scotia | $254,097 | $166,610 | $166,610 | - |
| 2014/2015 | National Defence | Atlantic Roofers | K10 - Upgrade roof, Gagetown, New Brunswick | $370,853 | $370,853 | $370,853 | - |
| 2014/2015 | National Defence | Atlantica Mechanical Contractors Inc | D201 Upgrade chillers 1 and 4, Halifax, Nova Scotia | $453,076 | $431,402 | $431,402 | - |
| 2014/2015 | National Defence | Aveiro Constructors Ltd | Beaver Hall Renovations Wolseley Barracks, London, Ontario | $735,009 | $722,478 | $722,478 | - |
| 2014/2015 | National Defence | Aztec Builders Ltd | Building 64 - Install Air Conditioner, Winnipeg, Manitoba | $686,378 | $666,689 | $676,689 | - |
| 2014/2015 | National Defence | Babcock Canada | Leasehold Improvement, Victoria, British Columbia | $7,978,895 | $7,978,895 | $7,978,895 | - |
| 2014/2015 | National Defence | Beland & Lapointe Inc | Geotechnical study/ topographical and environmental - Expansion of VC-362, Valcartier, Quebec | $2,027,479 | $2,024,479 | $2,024,479 | - |
| 2014/2015 | National Defence | Bell Multi Construction Inc | Recap 3 - 744 Style residential housing units CFHA Recap, Halifax, Nova Scotia | $452,849 | $423,942 | $423,942 | - |
| 2014/2015 | National Defence | Ben Wiebe Construction Ltd | Construct Artillery Observation Bunker, Shilo, Manitoba | $459,844 | $454,819 | $454,819 | - |
| 2014/2015 | National Defence | Ben Wiebe Construction Ltd | RCA Museum N118 Refurbish Exterior, Shilo, Manitoba | $614,889 | $37,702 | $614,889 | - |
| 2014/2015 | National Defence | Benchmark Construction Management Corp | Renovate Slave Tower, Cold Lake, Alberta | $305,200 | $7,400 | $7,400 | - |
| 2014/2015 | National Defence | Bergevin Electrical Contracting Ltd | Replace Electrical Systems Beatty Street Armoury, Vancouver, British Columbia | $283,426 | $0 | $150,333 | - |
| 2014/2015 | National Defence | Bernard Rochefort Ltd | Replace Boilers building 14, North Bay, Ontario | $555,281 | $555,281 | $555,281 | - |
| 2014/2015 | National Defence | Bervin Construction Ltd | Building 28 - Replace Generator - Electrical Code Violations, Abbotsford, British Columbia | $268,868 | $47,948 | $268,868 | - |
| 2014/2015 | National Defence | Bhullar's Construction Ltd | Upgrade Earth Cover and Approaches, Edmonton, Alberta | $391,350 | $391,350 | $391,350 | - |
| 2014/2015 | National Defence | Bighorn Construction Ltd | B414 Fire Hall Retrofit, Wainwright, Alberta | $502,795 | $317,577 | $317,577 | - |
| 2014/2015 | National Defence | Bighorn Construction Ltd | Construct MDF, Cold Lake, Alberta | $1,012,203 | $15,000 | $1,012,203 | - |
| 2014/2015 | National Defence | Bird Construction Group | Renovate Partial 2nd Floor, Halifax, Nova Scotia | $305,667 | $285,098 | $285,098 | - |
| 2014/2015 | National Defence | Bird Construction Inc | Building 21 Upgrade Men's Locker Room, Winnipeg, Manitoba | $702,035 | $231,910 | $702,035 | - |
| 2014/2015 | National Defence | Bird Design-Build Construction Inc | Design and Construction Pleasantville Consolidation Project, St John's, Newfoundland and Labrador | $125,117,367 | $1,067,988 | $125,034,608 | - |
| 2014/2015 | National Defence | Black & McDonald Ltd | Building 47 Construct HVAC system and install Exhaust Systems for Building 47 and Building 73, Winnipeg, Manitoba | $259,722 | $87,067 | $259,722 | - |
| 2014/2015 | National Defence | Black & McDonald Ltd | Replace HID Fixtures With LED Fixtures, Edmonton, Alberta | $286,330 | $149,139 | $149,139 | - |
| 2014/2015 | National Defence | Black & McDonald Ltd | Upgrade Burner System on Boilers 1 and 2, Halifax, Nova Scotia | $628,200 | $628,200 | $628,200 | - |
| 2014/2015 | National Defence | Black & McDonald Ltd | Upgrade Lights and Helicopter Signage, Halifax, Nova Scotia | $577,600 | $100,000 | $100,000 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | Install External Hookups for Back Up Boilers (S11), Halifax, Nova Scotia | $408,156 | $408,156 | $408,156 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | New Construction of Two Semi-Detached Modular Units, Halifax, Nova Scotia | $608,000 | $88,286 | $608,000 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | Replace Electrical Distribution & Emergency Shore Power CFAD Bedford, Halifax, Nova Scotia | $1,383,935 | $792,687 | $792,687 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | Replace Garages CFHA, Halifax, Nova Scotia | $460,912 | $460,912 | $460,912 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | S17 - Construct Distributed Missions Operations Centre (DMOC), Halifax, Nova Scotia | $376,962 | $0 | $376,962 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | Shearwater WTIS Upgrade - MDF, Halifax, Nova Scotia | $2,162,241 | $77,147 | $2,162,241 | - |
| 2014/2015 | National Defence | Blunden Construction Ltd | Upgrade ACS Ventilation System Hangar Z, Shearwater, Nova Scotia | $306,703 | $195,003 | $306,703 | - |
| 2014/2015 | National Defence | Bondfield Construction Company Ltd | Construction of Hangar 6, Quinte West, Ontario | $76,632,356 | $25,306,099 | $64,237,436 | - |
| 2014/2015 | National Defence | Bonnechere Excavating Inc | Construction of phases 1b & 2 in support of the MHLH facility, Petawawa, Ontario | $10,970,708 | $3,412,365 | $3,412,365 | - |
| 2014/2015 | National Defence | Bononia Construction Inc | Minor Recap 744 Style residential housing units, Quinte West, Ontario | $686,797 | $20,605 | $686,797 | - |
| 2014/2015 | National Defence | Brunnell Construction | Construct Outdoor Sports Facility - Improve Drainage and Provide Lighting, Victoria, British Columbia | $602,805 | $151,936 | $602,805 | - |
| 2014/2015 | National Defence | Buddy Haegele Enterprises Ltd | Construct Mezzanines for B479, Quinte West, Ontario | $272,000 | $116,402 | $272,000 | - |
| 2014/2015 | National Defence | Buddy Haegele Enterprises Ltd | Renovations to Senate Chamber, Kingston, Ontario | $423,862 | $6,598 | $423,862 | - |
| 2014/2015 | National Defence | Budget Environmental Disposal Inc | Deconstruct Building 113, Quinte West, Ontario | $351,595 | $2,825 | $351,595 | - |
| 2014/2015 | National Defence | Cabert Enterprises Ltd | Minor Recap 2 X B Style residential housing units, Cold Lake, Alberta | $722,030 | $673,795 | $673,795 | - |
| 2014/2015 | National Defence | Cabert Enterprises Ltd | Minor Recap 2 X H Style residential housing units, Cold Lake, Alberta | $555,121 | $30,219 | $555,121 | - |
| 2014/2015 | National Defence | Can-Sky Roofing and Sheet Metal Inc | Lower Roof Replacement - Fort York Armoury, Toronto, Ontario | $510,406 | $15,000 | $510,406 | - |
| 2014/2015 | National Defence | Canada Life Assurance Company | Edmonton Armoury - North, Edmonton, Alberta | $16,881,481 | $916,295 | $9,054,009 | - |
| 2014/2015 | National Defence | Carillion Canada Inc | Seismic Retrofit Seaforth Armoury and Relocate Jericho Beach Units, Vancouver, British Columbia | $33,364,716 | $18,958,422 | $22,278,068 | - |
| 2014/2015 | National Defence | Carillion Pacific Construction Inc | Seismic Retrofit Seaforth Armoury and Relocate Jericho Beach units, Vancouver, British Columbia | $43,136,472 | $20,965,735 | $33,188,138 | - |
| 2014/2015 | National Defence | Cas-Ell Structures Ltd | Standing offer agreement - General Trade Services - Rocky Mountain Cadet Camp and Cormack Armoury, Calgary, Alberta | $742,615 | $2,831 | $742,615 | - |
| 2014/2015 | National Defence | Cascade Roofing & Waterproofing Inc | Replace Roof Building 1082, Chilliwack, British Columbia | $329,172 | $329,172 | $329,172 | - |
| 2014/2015 | National Defence | Castle Rock Enterprises | Replace Whitehorse Cadet Camp On-Site Septic System, Whitehorse, Yukon | $544,868 | $477,053 | $477,053 | - |
| 2014/2015 | National Defence | Celeb Construction Ltd | Upgrade emergency exits Côte-des-Neiges, Montréal, Quebec | $312,480 | $15,430 | $312,480 | - |
| 2014/2015 | National Defence | Central Mechanical Systems Ltd | Replace Heating Oil Tank Piping, Yellowknife, Northwest Territories | $250,170 | $247,670 | $247,670 | - |
| 2014/2015 | National Defence | Ceriko Asselin Lombardi Inc | Building design, Montréal, Quebec | $6,509,360 | $43,309 | $6,509,360 | - |
| 2014/2015 | National Defence | Cevico Inc | Development B Div Janitorial Facilities, Bagotville, Quebec | $330,216 | $314,942 | $314,942 | - |
| 2014/2015 | National Defence | Chubb Edwards | Standing offer agreement - Alarm System, Edmonton, Alberta | $330,881 | $46,216 | $330,881 | - |
| 2014/2015 | National Defence | Churchill Construction Ltd | Extension to Firehall - Building 3, Happy Valley-Goose Bay, Newfoundland and Labrador | $522,703 | $10,000 | $522,703 | - |
| 2014/2015 | National Defence | Churchill Construction Ltd | Recap Two Semi-Detached Units (577 L/R), Happy Valley-Goose Bay, Newfoundland and Labrador | $554,490 | $15,000 | $554,490 | - |
| 2014/2015 | National Defence | Churchill Construction Ltd | Recap Two Semi-Detached Units in 500 Series (572 L/R), Happy Valley-Goose Bay, Newfoundland and Labrador | $545,736 | $442,736 | $442,736 | - |
| 2014/2015 | National Defence | Claveau & Fils Inc | Paving of Cadet Camp streets, Bagotville, Quebec | $472,228 | $431,857 | $431,857 | - |
| 2014/2015 | National Defence | Clearway Construction Inc | ASR/SSR Project Site Services Infrastructure, Winnipeg, Manitoba | $253,256 | $253,256 | $253,256 | - |
| 2014/2015 | National Defence | Clearway Construction Inc | Upgrade Water Sewer Storm communication and Road Systems - Phase 4, Cold Lake, Alberta | $23,722,438 | $15,979,667 | $22,961,026 | - |
| 2014/2015 | National Defence | Clotures Clermont Inc | Installation of S-E perimeter fences, Bagotville, Quebec | $354,250 | $343,295 | $343,295 | - |
| 2014/2015 | National Defence | Comox Consolidators Ltd | Minor Recap - CC & KK Style, Comox, British Columbia | $532,351 | $227,330 | $532,351 | - |
| 2014/2015 | National Defence | Con-Pro Industries Canada Ltd | B72 Provide Central Air, Winnipeg, Manitoba | $788,695 | $701,619 | $701,619 | - |
| 2014/2015 | National Defence | Construction Jessiko Inc | Conduct geothermal conductivity test on former L-12 Site, Montréal, Quebec | $680,244 | $653,629 | $653,629 | - |
| 2014/2015 | National Defence | Construction Mafranc Inc | Renovate ventilation system - La Citadelle de Québec, Québec, Quebec | $301,500 | $98,342 | $301,500 | - |
| 2014/2015 | National Defence | Construction TransParent/ 9222-0342 | Recap and make compliant POL facilities at VC-367, Valcartier, Quebec | $348,753 | $343,753 | $343,753 | - |
| 2014/2015 | National Defence | Constructions C R Les | Upgrade Kitchen 3 Wing, Bagotville, Quebec | $723,193 | $723,192 | $723,192 | - |
| 2014/2015 | National Defence | Contracts under $250,000 and cost plus contracts under $25,000 (777 contractors) | Total | $0 | $36,104,732 | $0 | - |
| 2014/2015 | National Defence | Cooney Excavating | ASR/SSR Project Site Services Infrastructure, Quinte West, Ontario | $359,473 | $0 | $0 | - |
| 2014/2015 | National Defence | Correctional Services Canada | Emergency Replacement - Accommodations, Ottawa, Ontario | $899,484 | $330,204 | $330,204 | - |
| 2014/2015 | National Defence | Daoust Construction | Demolition and construction to re-fit the 7th floor Pearkes, Ottawa, Ontario | $3,341,493 | $1,769,694 | $1,957,860 | - |
| 2014/2015 | National Defence | Darpak Inc | Reconstruct Argus Crescent, Borden, Ontario | $427,720 | $427,720 | $427,720 | - |
| 2014/2015 | National Defence | Dave McDonald Electric Ltd | Replace UPS Systems - Dockyard 199, Victoria, British Columbia | $544,571 | $268,231 | $544,571 | - |
| 2014/2015 | National Defence | Dave McDonald Electric Ltd | Upgrade and Enhance Current Dockyard Camera System, Esquimalt, British Columbia | $359,500 | $159,676 | $159,676 | - |
| 2014/2015 | National Defence | David J Cupido Construction Ltd | R62 Renovations - Environmental Sciences Group, Kingston, Ontario | $511,810 | $134,914 | $511,810 | - |
| 2014/2015 | National Defence | Delmar Construction Ltd | Construct troop shelters Yarmouth armouries, Greenwood, Nova Scotia | $674,543 | $644,224 | $644,224 | - |
| 2014/2015 | National Defence | Desjardins Wealth Management | Shawinigan Armoury, Shawinigan, Quebec | $6,782,082 | $433,016 | $4,341,183 | - |
| 2014/2015 | National Defence | Dexter Construction Company Ltd | Deconstruct Old Shearwater CHP SH56, Shearwater, Nova Scotia | $789,048 | $589,048 | $789,048 | - |
| 2014/2015 | National Defence | Dig-Con International Ltd | Renovations to MacKenzie Offices, Kingston, Ontario | $616,640 | $8,100 | $616,640 | - |
| 2014/2015 | National Defence | Don Saywell Developments Ltd | Standing offer agreement - General Construction, Comox, British Columbia | $1,000,000 | $91,976 | $721,669 | - |
| 2014/2015 | National Defence | Don Saywell Developments Ltd | Upgrade Roof Building 171, Comox, British Columbia | $432,802 | $427,302 | $427,302 | - |
| 2014/2015 | National Defence | Duggan Electric Ltd | Upgrade High Bay Lighting Various Buildings - Hangar 342 & 344, Halifax, Nova Scotia | $464,597 | $300,000 | $300,000 | - |
| 2014/2015 | National Defence | East Central Painting & Coating Services Inc | Parking Lot Improvement, Wainwright, Alberta | $448,789 | $448,789 | $448,789 | - |
| 2014/2015 | National Defence | East Central Painting & Coating Services Inc | Tie-in New Waterline to Meter, Wainwright, Alberta | $453,245 | $449,745 | $449,745 | - |
| 2014/2015 | National Defence | Eastern Fence Erectors Ltd | Upgrade Perimeter Security Fence, Greenwood, Nova Scotia | $449,300 | $405,384 | $405,384 | - |
| 2014/2015 | National Defence | Eastern Restoration Services Inc | Construct Male and Female Locker Rooms Hangar 10, Greenwood, Nova Scotia | $425,000 | $0 | $328,259 | - |
| 2014/2015 | National Defence | Eastway Contracting Inc | Medium heavy lift helicopters municipal utility services, Petawawa, Ontario | $6,033,504 | $14,500 | $6,033,504 | - |
| 2014/2015 | National Defence | Edgeline Construction Ltd | B-9 - Upgrade for Change of Use, Gagetown, New Brunswick | $403,149 | $373,149 | $373,149 | - |
| 2014/2015 | National Defence | Edgeline Construction Ltd | Renovations to a Portion of K6, Gagetown, New Brunswick | $353,073 | $315,485 | $353,073 | - |
| 2014/2015 | National Defence | EllisDon Construction Services Inc | Tactical Armoured Patrol Vehicle, Edmonton, Alberta | $1,280,284 | $388,672 | $388,672 | - |
| 2014/2015 | National Defence | EllisDon Corporation | Declaration of Interest for preselection of design builders hangars, Petawawa, Ontario | $154,005,371 | $7,769,448 | $153,315,723 | - |
| 2014/2015 | National Defence | EllisDon Corporation | Upgrade Sawyer complex, Kingston, Ontario | $126,624,157 | $16,577,505 | $98,247,623 | - |
| 2014/2015 | National Defence | EllisDon Corporation / Kinetic Construction Ltd in Joint Venture | General construction services - FMF, Esquimalt, British Columbia | $184,930,026 | $53,139,459 | $61,119,264 | - |
| 2014/2015 | National Defence | Entreprises QMD Inc | Expand kitchen St-Jean Garrison, Saint-Jean-sur-Richelieu, Quebec | $10,212,630 | $6,240,737 | $8,269,789 | - |
| 2014/2015 | National Defence | Essa Sewer & Plumbing Inc | Minor Recap PP Style 2 residential housing units, Borden, Ontario | $315,441 | $310,941 | $310,941 | - |
| 2014/2015 | National Defence | Evolve Exteriors Inc | Exterior Retrofit, Cold Lake, Alberta | $1,888,060 | $1,686,971 | $1,686,971 | - |
| 2014/2015 | National Defence | Evolvecomp Construction Inc | Minor Recap 2 X KK 54S Style residential housing units, Cold Lake, Alberta | $1,590,790 | $1,544,762 | $1,544,762 | - |
| 2014/2015 | National Defence | Excel-7 Ltd | Construct Demolition Bunker, Shilo, Manitoba | $487,431 | $478,402 | $478,402 | - |
| 2014/2015 | National Defence | Excel-7 Ltd | Install Sprinkler System Brandon Armouries, Shilo, Manitoba | $478,929 | $437,398 | $478,929 | - |
| 2014/2015 | National Defence | Farmer Construction Ltd | Standing Offer Agreement - General construction, Esquimalt, British Columbia | $2,378,264 | $0 | $2,378,264 | - |
| 2014/2015 | National Defence | Firstonsite Restoration | General Construction - Standing Offer Agreement, Shilo, Manitoba | $272,537 | $0 | $272,537 | - |
| 2014/2015 | National Defence | Flint Field Services Ltd | Design of Headworks Screens for the WWTP, Cold Lake, Alberta | $525,500 | $524,480 | $524,480 | - |
| 2014/2015 | National Defence | Flynn Canada Ltd | B1 - Upgrade Roof, Gagetown, New Brunswick | $393,256 | $393,256 | $393,256 | - |
| 2014/2015 | National Defence | Frecon Construction Ltd | Construct ERU Building, Petawawa, Ontario | $1,567,000 | $468,525 | $468,525 | - |
| 2014/2015 | National Defence | Frecon Construction Ltd | Construct Extension to Existing Building, Petawawa, Ontario | $1,369,951 | $236,915 | $1,369,951 | - |
| 2014/2015 | National Defence | Frecon Construction Ltd | Renovate Office Space in Building M-105 Garrison, Petawawa, Ontario | $468,167 | $115,921 | $468,167 | - |
| 2014/2015 | National Defence | Frecon Construction Ltd | Upgrade Fire Suppression Equipment in Building Y-101, Petawawa, Ontario | $479,940 | $264,494 | $479,940 | - |
| 2014/2015 | National Defence | Frecon Construction Ltd | Upgrade Maintenance Pit D-104, Petawawa, Ontario | $262,408 | $198,542 | $198,542 | - |
| 2014/2015 | National Defence | G A Leblanc Construction and Services | BM212 Electrical and Architectural Upgrades, Halifax, Nova Scotia | $429,944 | $374,944 | $429,944 | - |
| 2014/2015 | National Defence | G A Leblanc Construction and Services | S7 Chapel Window Replacement, Halifax, Nova Scotia | $270,000 | $265,000 | $265,000 | - |
| 2014/2015 | National Defence | G C P Construction Inc | Upgrade furniture and lighting in 5 amphitheatres - St-Jean Garrison, Saint-Jean-sur-Richelieu, Quebec | $335,259 | $335,259 | $335,259 | - |
| 2014/2015 | National Defence | GWL Realty Advisors Inc | Edmonton Armoury - South, Edmonton, Alberta | $21,495,129 | $1,319,802 | $9,222,957 | - |
| 2014/2015 | National Defence | Gabriel Construction Alberta Ltd | Repair Roof Over Fitness Coordinator's Office - Building 35, Gander, Newfoundland and Labrador | $6,180,123 | $164,904 | $6,180,123 | - |
| 2014/2015 | National Defence | Gary Parker Excavating Ltd | Construct New Hazmat Storage Building, Greenwood, Nova Scotia | $612,198 | $0 | $612,198 | - |
| 2014/2015 | National Defence | Gary Parker Excavating Ltd | Expand Parking Lot for various lodges, Greenwood, Nova Scotia | $257,000 | $257,000 | $257,000 | - |
| 2014/2015 | National Defence | Ger-Ro Construction Inc | Construct of building for CFHA, Bagotville, Quebec | $670,058 | $521,823 | $521,823 | - |
| 2014/2015 | National Defence | Germain Construction Inc | Make compliant POL storage facilities, Valcartier, Quebec | $644,427 | $0 | $0 | - |
| 2014/2015 | National Defence | Germain Construction Inc | Recap types JJ/ CC/ M-143/ K and KK lodgings, Valcartier, Quebec | $1,902,832 | $1,748,072 | $1,748,072 | - |
| 2014/2015 | National Defence | Germain Construction Inc | Upgrade storage tanks and consultant services, Valcartier, Quebec | $529,247 | $524,247 | $524,247 | - |
| 2014/2015 | National Defence | Gil-Son Construction Ltd | Replace Main High Voltage Switchgear, Greenwood, Nova Scotia | $725,410 | $391,930 | $391,930 | - |
| 2014/2015 | National Defence | Gil-Son Construction Ltd | Upgrade 4 16/ 2 4 KV Substation to 12 47/ 7 2, Greenwood, Nova Scotia | $661,922 | $382,040 | $382,040 | - |
| 2014/2015 | National Defence | Gil-Son Construction Ltd | Upgrade Main Substation - Shearwater, Halifax, Nova Scotia | $676,600 | $0 | $0 | - |
| 2014/2015 | National Defence | Graham Construction and Engineering Inc | Canadian Forces Military Police Academy, Angus, Ontario | $33,115,111 | $13,919,451 | $31,819,146 | - |
| 2014/2015 | National Defence | Graham Construction and Engineering Inc | Construct hangar 2, Quinte West, Ontario | $47,642,185 | $853,755 | $47,642,185 | - |
| 2014/2015 | National Defence | Graham Construction and Engineering Inc | New Integrated Healthcare Services Centre, Borden, Ontario | $18,863,040 | $6,692,376 | $8,666,172 | - |
| 2014/2015 | National Defence | Greendale Resources Inc | Construct Fire Training Tower Shearwater & Dockyard, Halifax, Nova Scotia | $511,000 | $8,625 | $8,625 | - |
| 2014/2015 | National Defence | Groupe AllaireGince Infrastructures Inc | Upgrade of roads and ditches Sectors 2B-1 4D and 4G, Farnham, Quebec | $399,145 | $399,145 | $399,145 | - |
| 2014/2015 | National Defence | Groupe BGR Construction Inc | Construction new museum warehouse Building 394, Bagotville, Quebec | $621,474 | $562,203 | $562,203 | - |
| 2014/2015 | National Defence | Groupe Beaudoin Inc | Replace condenser tanks and #2 boiler tank - Thermal Power Plant - La Citadelle de Québec, Québec, Quebec | $1,274,815 | $55,440 | $1,274,815 | - |
| 2014/2015 | National Defence | Groupe LML | Replace a generator, Saint-Jean-sur-Richelieu, Quebec | $528,903 | $521,803 | $528,903 | - |
| 2014/2015 | National Defence | Groupe Piche Construction Inc | Funded Standing offer agreement - General Contractors, Montréal, Quebec | $319,946 | $255 | $319,946 | - |
| 2014/2015 | National Defence | Habitations Consultants H L Inc | Build two easy-access transitional accommodations - Valcartier Garrison, Courcelette, Quebec | $1,018,165 | $79,208 | $1,018,165 | - |
| 2014/2015 | National Defence | Harrington Plumbing & Heating Ltd | Interior Renovations in Building Z106, Petawawa, Ontario | $458,793 | $288,019 | $458,793 | - |
| 2014/2015 | National Defence | Heron Enterprises Inc | K-15 Upgrade for Change of Use, Gagetown, New Brunswick | $252,880 | $101,152 | $101,152 | - |
| 2014/2015 | National Defence | Heron Enterprises Inc | Recap residential housing units 4 M/341/331 Row Style residential housing units CFHA, Gagetown, New Brunswick | $302,030 | $302,030 | $302,030 | - |
| 2014/2015 | National Defence | Hexagon Construction Ltd | Recap 6 - residential housing units CFHA, Gagetown, New Brunswick | $545,735 | $523,735 | $523,735 | - |
| 2014/2015 | National Defence | High Line Electrical Constructors Ltd | Upgrade Fire Alarm and Gas Detection System - Hazmat Storage Facility, Edmonton, Alberta | $360,416 | $0 | $360,416 | - |
| 2014/2015 | National Defence | Holland Contracting Inc E | Upgrade Base Roadway Lighting, Gagetown, New Brunswick | $403,934 | $327,070 | $327,070 | - |
| 2014/2015 | National Defence | Houle Electric Ltd | Electrical Construction - Standing Offer Agreement, Victoria, British Columbia | $1,167,942 | $6,227 | $1,167,942 | - |
| 2014/2015 | National Defence | Hydro Ottawa | Leitrim Road Construction, Ottawa, Ontario | $842,980 | $1,633 | $672,161 | - |
| 2014/2015 | National Defence | Intact Insurance Company | Vehicle Maintenance Facility, Wainwright, Alberta | $40,555,333 | $14,776,307 | $32,822,404 | - |
| 2014/2015 | National Defence | Irvcon Ltd | Replace Pool Dehumidification Unit, Petawawa, Ontario | $527,550 | $194,836 | $527,550 | - |
| 2014/2015 | National Defence | Island West Coast Developments Ltd | Healthcare facility, Comox, British Columbia | $13,895,517 | $104,624 | $13,895,517 | - |
| 2014/2015 | National Defence | Island West Coast Developments Ltd | Replace Compressors in H-7 & H-14, Comox, British Columbia | $416,382 | $16,322 | $416,382 | - |
| 2014/2015 | National Defence | J & J Enterprises Ltd | Minor Recap 6Plex residential housing units, Gander, Newfoundland and Labrador | $756,668 | $426,975 | $426,975 | - |
| 2014/2015 | National Defence | J W Lindsay Enterprises Ltd | Design and build cadet accommodation buildings, Gagetown, New Brunswick | $13,262,656 | $1,060,485 | $13,258,073 | - |
| 2014/2015 | National Defence | JES Construction Inc | Expand Parking Lot - Saint-Malo Armoury, Québec, Quebec | $276,447 | $5,000 | $276,447 | - |
| 2014/2015 | National Defence | Jasper Construction Corporation | Construct Storage Buildings and Hazardous Waste Facility, Quinte West, Ontario | $6,069,184 | $4,323,425 | $4,323,425 | - |
| 2014/2015 | National Defence | Jetco Contracting Inc | Accommodate New Bcomd Staff, Halifax, Nova Scotia | $268,619 | $268,619 | $268,619 | - |
| 2014/2015 | National Defence | Jetco Contracting Inc | Halifax Recap 2 744 Style residential housing units, Halifax, Nova Scotia | $307,562 | $281,697 | $281,697 | - |
| 2014/2015 | National Defence | Joe Pace & Sons Contracting Inc | Minor Recap residential housing units, Borden, Ontario | $1,409,511 | $694,461 | $1,409,511 | - |
| 2014/2015 | National Defence | John MacKay Painting and Flooring | Upgrade Barrier Free Access in Various Buildings, Petawawa, Ontario | $397,393 | $240,639 | $397,393 | - |
| 2014/2015 | National Defence | John MacKay Painting and Flooring | Upgrade I Mod of Building G103, Petawawa, Ontario | $347,659 | $347,659 | $347,659 | - |
| 2014/2015 | National Defence | K Knudsen Construction Ltd | Recap 744 Style residential housing units, Quinte West, Ontario | $503,791 | $503,791 | $503,791 | - |
| 2014/2015 | National Defence | K-Line Construction Ltd | Upgrade Camp Argo Utilitiy Poles 5 CDSB, Gagetown, New Brunswick | $266,117 | $245,248 | $245,248 | - |
| 2014/2015 | National Defence | K-Rite Construction Ltd | Fire Hall Building 186 Alarm Room and Renovations, Edmonton, Alberta | $755,513 | $596,582 | $749,721 | - |
| 2014/2015 | National Defence | K-Rite Construction Ltd | Standing offer agreement - Tank Compliance Upgrades, Edmonton, Alberta | $452,041 | $291,767 | $452,041 | - |
| 2014/2015 | National Defence | KDB Engineers/Contractors Inc | Worthington Road Upgrade Portion of MSR 5 CDSB, Gagetown, New Brunswick | $773,849 | $773,849 | $773,849 | - |
| 2014/2015 | National Defence | KDR Design Builders Commercial Inc | Construction of New Alert Locker Building, Shilo, Manitoba | $3,039,915 | $1,335,185 | $3,039,915 | - |
| 2014/2015 | National Defence | Karson Kartage and Konstruction Ltd | Leitrim Road Construction, Ottawa, Ontario | $4,305,664 | $48,324 | $4,305,664 | - |
| 2014/2015 | National Defence | Keller Construction Ltd | Canadian manoeuvre training centre facility, Wainwright, Alberta | $15,824,742 | $175,222 | $15,824,742 | - |
| 2014/2015 | National Defence | Kenalex Construction Company Ltd | Replace Building 23 Humidification Units, North Bay, Ontario | $747,242 | $747,242 | $747,242 | - |
| 2014/2015 | National Defence | Key West Civil Contracting Ltd | Standing offer agreement - Construction services, Chilliwack, British Columbia | $1,199,400 | $159,117 | $793,664 | - |
| 2014/2015 | National Defence | Kinetic Construction Ltd | Personnel Support Centre, Comox, British Columbia | $2,055,633 | $246,145 | $246,145 | - |
| 2014/2015 | National Defence | Kinetic Construction Ltd | Replace Building Systems - Dockyard Building 70, Esquimalt, British Columbia | $2,289,712 | $835,434 | $835,434 | - |
| 2014/2015 | National Defence | King Construction Ltd | Construct Commissionaire's Hut 5 CDSB, Gagetown, New Brunswick | $314,192 | $309,192 | $309,192 | - |
| 2014/2015 | National Defence | King Construction Ltd | J-8 Upgrade for Change of Use, Gagetown, New Brunswick | $276,469 | $276,469 | $276,469 | - |
| 2014/2015 | National Defence | King Construction Ltd | Purchase/Install Portable Weapons Lockup, Gagetown, New Brunswick | $312,727 | $311,918 | $311,918 | - |
| 2014/2015 | National Defence | Knappett Projects Inc | Maritime helicopter squadron facility, Esquimalt, British Columbia | $106,707,880 | $7,424,699 | $106,276,419 | - |
| 2014/2015 | National Defence | Krawford Construction Inc | Vehicle maintenance facility, Wainwright, Alberta | $42,255,000 | $14,290,291 | $32,336,388 | - |
| 2014/2015 | National Defence | Laser Shot Inc | Construct Indoor Shooting Range with Virtual Targetry, Petawawa, Ontario | $3,568,869 | $67,352 | $3,568,869 | - |
| 2014/2015 | National Defence | Le Groupe Decarel Inc | Construction of infrastructure for light armoured vehicle, Courcelette, Quebec | $17,076,743 | $515,291 | $16,991,743 | - |
| 2014/2015 | National Defence | Lynley Painting Ltd | New Sheds, Borden, Ontario | $1,496,914 | $1,274,914 | $1,274,914 | - |
| 2014/2015 | National Defence | M J Dixon Construction Ltd | Construct firehall, Quinte West, Ontario | $12,823,672 | $124,100 | $12,823,672 | - |
| 2014/2015 | National Defence | M J Roy Enterprises Ltd | Replace Garages CFHA, Gagetown, New Brunswick | $560,852 | $879,427 | $560,852 | - |
| 2014/2015 | National Defence | M Sullivan & Son Ltd | Construction of the Tactical Armoured Patrol Vehicle Building, Petawawa, Ontario | $1,162,059 | $704,046 | $1,069,648 | - |
| 2014/2015 | National Defence | MX Renovations Ltd | Exterior Retrofit R315/B, Shilo, Manitoba | $366,000 | $366,000 | $366,000 | - |
| 2014/2015 | National Defence | Maddocks Construction Ltd | Retrofit Building B26 - VACTC, Chilliwack, British Columbia | $311,122 | $311,122 | $311,122 | - |
| 2014/2015 | National Defence | Mafranc Inc | Recap kitchen ventilation system VC-514, Valcartier, Quebec | $287,667 | $287,667 | $287,667 | - |
| 2014/2015 | National Defence | Mafranc Inc | Ventilation system change DRDC, Valcartier, Quebec | $323,890 | $3,600 | $3,600 | - |
| 2014/2015 | National Defence | Maram Building Corp | All ranks dining facility, Borden, Ontario | $20,326,123 | $1,521,612 | $19,798,209 | - |
| 2014/2015 | National Defence | Marc Bolduc Inc | Full renovation of kitchens and bathrooms, Valcartier, Quebec | $618,057 | $611,907 | $611,907 | - |
| 2014/2015 | National Defence | Marc Thomassin Inc | Convert a building to a ballistics laboratory DRDC, Courcelette, Quebec | $407,905 | $13,766 | $407,905 | - |
| 2014/2015 | National Defence | Marco Maritimes Ltd | Upgrade Building 1 - DRDC Atlantic Construction, Halifax, Nova Scotia | $27,996,101 | $13,814,743 | $25,202,995 | - |
| 2014/2015 | National Defence | Maricon Construction Management Ltd | Improvements to K20 Petroleum Oil Lubricant Compound, Oromocto, New Brunswick | $6,501,269 | $1,808,478 | $6,501,269 | - |
| 2014/2015 | National Defence | Massicotte Construction Ltd | Construction of AvPOL Facility, Petawawa, Ontario | $9,344,953 | $378,839 | $9,344,953 | - |
| 2014/2015 | National Defence | Mauco Inc | Upgrade swimming pool, Saguenay, Quebec | $531,046 | $65,350 | $531,046 | - |
| 2014/2015 | National Defence | Maxi-Paysage Inc | Raising of electronic scale at VC-540, Valcartier, Quebec | $403,716 | $403,716 | $403,716 | - |
| 2014/2015 | National Defence | Maxim 2000 Inc | CF weather and oceanographic service transformation - Renovations and additions, Gagetown, New Brunswick | $5,571,064 | $62,583 | $5,571,064 | - |
| 2014/2015 | National Defence | Maxim 2000 Inc | Edmunston Armoury, Edmundston, New Brunswick | $5,173,462 | $751,289 | $5,173,462 | - |
| 2014/2015 | National Defence | Maxim Construction Inc | Replace Central Heating System Design Services, Bedford, Nova Scotia | $1,896,562 | $712,526 | $712,526 | - |
| 2014/2015 | National Defence | Mayer's Contract Interiors Ltd | Recap of 2 JJ & GG Style residential housing units, Winnipeg, Manitoba | $398,000 | $263,823 | $263,823 | - |
| 2014/2015 | National Defence | McClement Electric Ltd | Electrical Upgrade Vimy Officers' Mess, Kingston, Ontario | $681,537 | $659,137 | $659,137 | - |
| 2014/2015 | National Defence | McDonald Bros Construction Inc | 427 Special Operations Aviation Squadron (SOAS) Transport and Maintenance (TEME) Facility, Petawawa, Ontario | $5,651,000 | $0 | $0 | - |
| 2014/2015 | National Defence | McDonald Bros Construction Inc | Construct training accommodations for MHLH, Petawawa, Ontario | $12,572,818 | $130,155 | $12,548,156 | - |
| 2014/2015 | National Defence | McDonald Bros Construction Inc | Leitrim Bulk Storage Facility, Ottawa, Ontario | $2,133,000 | $0 | $0 | - |
| 2014/2015 | National Defence | Mealy Mountain Contracting Ltd | Heat System Conversions 600 Area, Happy Valley-Goose Bay, Newfoundland and Labrador | $463,131 | $314,514 | $314,514 | - |
| 2014/2015 | National Defence | Melville Trucking & Excavating Ltd | Extension to Kittyhawk Road, Happy Valley-Goose Bay, Newfoundland and Labrador | $335,157 | $335,157 | $335,157 | - |
| 2014/2015 | National Defence | Michanie Construction Inc | Cabling & Environmental Upgrade, Ottawa, Ontario | $761,212 | $559,384 | $559,384 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Connect PW#9 to Domestic OPS, Greenwood, Nova Scotia | $303,718 | $303,718 | $303,718 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Construct New QRA, Greenwood, Nova Scotia | $668,338 | $663,338 | $663,338 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Fence Clearance Lights and Airfield Sign, Shearwater, Nova Scotia | $660,112 | $260,112 | $660,112 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | High Voltage Distribution Feeder Replacement, Greenwood, Nova Scotia | $442,970 | $442,970 | $442,970 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Install New High Voltage Feeder - Airfield Loop, Greenwood, Nova Scotia | $475,854 | $20,000 | $475,854 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Install Sprinkler System B165 Argus House, Greenwood, Nova Scotia | $473,769 | $459,017 | $459,017 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Install new high voltage switch domestic east, Greenwood, Nova Scotia | $482,962 | $482,962 | $482,962 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Install new high voltage switch domestic west, Greenwood, Nova Scotia | $251,185 | $251,185 | $251,185 | - |
| 2014/2015 | National Defence | Mid-Valley Construction Ltd | Recap 4 CC Style residential housing units, Greenwood, Nova Scotia | $360,184 | $360,184 | $360,184 | - |
| 2014/2015 | National Defence | Modern Niagara HVAC Services Inc | Standing offer agreement - General Construction, Kingston, Ontario | $982,450 | $463,340 | $908,107 | - |
| 2014/2015 | National Defence | Monteith Building Group | Building A-245 Addition Extension Modification, Borden, Ontario | $2,551,521 | $29,959 | $2,551,521 | - |
| 2014/2015 | National Defence | Montfort Health Services | Montfort Hospital - Health Services, Ottawa, Ontario | $74,219,313 | $2,960,881 | $34,397,535 | - |
| 2014/2015 | National Defence | Muchalat Projects Ltd | Build Conventional framed residential housing units, Esquimalt, British Columbia | $837,584 | $616,943 | $837,584 | - |
| 2014/2015 | National Defence | Muchalat Projects Ltd | Construction of Day-Care Facility, Comox, British Columbia | $930,336 | $23,617 | $930,336 | - |
| 2014/2015 | National Defence | Muchalat Projects Ltd | Construction of New Single Quarters, Comox, British Columbia | $931,666 | $50,658 | $931,666 | - |
| 2014/2015 | National Defence | Muchalat Projects Ltd | Long Term Accommodations, Comox, British Columbia | $656,676 | $645,578 | $645,578 | - |
| 2014/2015 | National Defence | N A P Windows and Doors Ltd | Upgrades-Window Replacement Building Envelope/Efficiency, Cold Lake, Alberta | $349,243 | $11,474 | $349,243 | - |
| 2014/2015 | National Defence | NRG Management | HVAC Retrofit, Shilo, Manitoba | $319,232 | $254,116 | $254,116 | - |
| 2014/2015 | National Defence | Nails Enterprises Inc | Construct Offices 1 AMS, Cold Lake, Alberta | $428,658 | $253,463 | $253,463 | - |
| 2014/2015 | National Defence | Nails Enterprises Inc | Install A/C BB43 and BB45, Cold Lake, Alberta | $660,000 | $74,879 | $74,879 | - |
| 2014/2015 | National Defence | Norich Electric Ltd | Standing offer agreement - General Electrical Maintenance, Chilliwack, British Columbia | $367,253 | $0 | $367,253 | - |
| 2014/2015 | National Defence | Norm Smith Electric Ltd | Replace High Voltage Switchgear, Greenwood, Nova Scotia | $557,960 | $324,839 | $324,839 | - |
| 2014/2015 | National Defence | Norm Smith Electric Ltd | Upgrade B250 electrical and mechanical systems, Greenwood, Nova Scotia | $502,455 | $500,455 | $500,455 | - |
| 2014/2015 | National Defence | Northern Construction Inc | Grand Falls Armoury Upgrades to Parking Area, Gagetown, New Brunswick | $737,423 | $722,423 | $722,423 | - |
| 2014/2015 | National Defence | Nortuk Contracting Ltd | Building A-154 New Fuel Tanks CHP 37 Spitfire Lane, Borden, Ontario | $559,165 | $83,393 | $559,165 | - |
| 2014/2015 | National Defence | Norwin Roofing Ltd | B52-Replace Roof, Winnipeg, Manitoba | $383,749 | $183,803 | $383,749 | - |
| 2014/2015 | National Defence | Ottawa River Power Corporation | Small Construction and Repairs of High Voltage Distribution System - Standing Offer Agreement, Petawawa, Ontario | $500,000 | $188,495 | $308,209 | - |
| 2014/2015 | National Defence | P C McNeill Contracting Ltd | CFHA Minor Recap MM Style residential housing units, Kingston, Ontario | $583,182 | $9,260 | $583,182 | - |
| 2014/2015 | National Defence | PCL Constructors Canada | Construct New Bedford Armoury, Halifax, Nova Scotia | $6,616,157 | $6,344,297 | $6,344,297 | - |
| 2014/2015 | National Defence | PCL Constructors Canada | TAPV - Gagetown tactical armoured patrol vehicle infra-studies, Gagetown, New Brunswick | $788,200 | $383,356 | $383,356 | - |
| 2014/2015 | National Defence | PCL Constructors Canada | Victoria class syncrolift improvement - General construction contract, Halifax, Nova Scotia | $42,191,016 | $362,156 | $42,191,016 | - |
| 2014/2015 | National Defence | PCR Contractors Inc | HMCS Hunter Replacement, London, Ontario | $18,731,225 | $6,187,029 | $18,573,614 | - |
| 2014/2015 | National Defence | Parthian Mechanical Inc | MB52 - HVAC Upgrades, Kingston, Ontario | $473,312 | $17,118 | $473,312 | - |
| 2014/2015 | National Defence | Peak Engineering & Construction Ltd | Central region gliding school hangar, Quinte West, Ontario | $11,010,472 | $0 | $10,887,830 | - |
| 2014/2015 | National Defence | Pentagon Structures Ltd | Building 700, Edmonton, Alberta | $34,149,741 | $5,216,461 | $33,924,640 | - |
| 2014/2015 | National Defence | Pentagon Structures Ltd | Training accommodation facility, Edmonton, Alberta | $12,106,695 | $61,312 | $12,106,695 | - |
| 2014/2015 | National Defence | Philson Ltd | Refurbishment of Tunnel System - Phase IV, Oromocto, New Brunswick | $13,402,506 | $5,131,356 | $13,152,506 | - |
| 2014/2015 | National Defence | Pierre Blouin Inc | Expansion of mechanical room and replacement of pool mechanical systems VC-516, Valcartier, Quebec | $2,179,815 | $739,281 | $739,281 | - |
| 2014/2015 | National Defence | Plenary Properties | Public-private partnership arrangement to design build and finance, Ottawa, Ontario | $1,170,095,399 | $304,816,915 | $304,816,915 | - |
| 2014/2015 | National Defence | Plomberie Laroche Inc | Replacement of exchangers, Valcartier, Quebec | $278,525 | $238,859 | $238,859 | - |
| 2014/2015 | National Defence | Poly-Toiture Inc | Recap of IV B-216 roof, Bagotville, Quebec | $305,216 | $136,071 | $136,071 | - |
| 2014/2015 | National Defence | Pomerleau Inc Darmouth | Refurbishment of Tunnel System Phase V, Oromocto, New Brunswick | $21,118,870 | $428,595 | $21,118,870 | - |
| 2014/2015 | National Defence | Pomerleau Inc Québec | Design-Builder Services for Tactical Armoured Patrol Vehicle, Courcelette, Quebec | $1,630,045 | $1,320,091 | $1,536,309 | - |
| 2014/2015 | National Defence | Power-Tek Capital Services Inc | Capabilities - Structural Extension, Ottawa, Ontario | $381,975 | $376,975 | $381,975 | - |
| 2014/2015 | National Defence | Preview Builders International Inc | Base fire hall and emergency response centre, Esquimalt, British Columbia | $21,656,817 | $738,210 | $21,656,817 | - |
| 2014/2015 | National Defence | Quad Pro Construction Inc | Construct building for recruiting group, Borden, Ontario | $5,626,799 | $60,746 | $5,626,799 | - |
| 2014/2015 | National Defence | Quinan Construction Ltd | Masset Operations Building Recapitalization Asbestos Abatement, Esquimalt, British Columbia | $2,196,000 | $0 | $0 | - |
| 2014/2015 | National Defence | R W K Construction Co Ltd | Install Mezzanines Building 404, Edmonton, Alberta | $436,677 | $436,677 | $436,677 | - |
| 2014/2015 | National Defence | R W K Construction Co Ltd | Recap three 213 Style Residential Housing Unit, Edmonton, Alberta | $480,795 | $324,588 | $324,588 | - |
| 2014/2015 | National Defence | RGT Clouthier Construction Ltd | Construct apron and runway, Petawawa, Ontario | $39,500,412 | $2,120,236 | $39,480,411 | - |
| 2014/2015 | National Defence | Ranova Enterprises Inc | Kitchen and Bathroom Renovations, Quinte West, Ontario | $345,681 | $345,681 | $345,681 | - |
| 2014/2015 | National Defence | Ravencor Projects Inc | Building 354 Install New Air Conditioning, Happy Valley-Goose Bay, Newfoundland and Labrador | $570,625 | $453,690 | $453,690 | - |
| 2014/2015 | National Defence | Reliance Protectron Inc | Intrusion Alarm Upgrade, Winnipeg, Manitoba | $646,808 | $349,861 | $589,851 | - |
| 2014/2015 | National Defence | Roscoe Construction Ltd | Install 100 000 lb hoist h007, Greenwood, Nova Scotia | $308,544 | $265,357 | $265,357 | - |
| 2014/2015 | National Defence | Ruiter Construction Ltd | HMCS Carleton Replacement, Ottawa, Ontario | $14,372,461 | $9,011,789 | $12,652,903 | - |
| 2014/2015 | National Defence | Rushworth Electrical Services Inc | Electrical Construction - Standing Offer Agreement, Victoria, British Columbia | $1,800,000 | $88,967 | $1,791,810 | - |
| 2014/2015 | National Defence | Rushworth Electrical Services Inc | Mechanical and Electrical System Upgrade, Esquimalt, British Columbia | $632,893 | $632,893 | $632,893 | - |
| 2014/2015 | National Defence | Rushworth Electrical Services Inc | Naden 92A - New Underground Service From HV Switch, Victoria, British Columbia | $276,736 | $118,711 | $276,736 | - |
| 2014/2015 | National Defence | Scansa Construction Ltd | Construct Utlity Corridor - Phase 4, Esquimalt, British Columbia | $27,145,243 | $3,581,310 | $27,145,243 | - |
| 2014/2015 | National Defence | Seafirst Construction Corp | Replace Fuel Tank Building D-1, Whitehorse, Northwest Territories | $377,858 | $56,112 | $377,858 | - |
| 2014/2015 | National Defence | Senator Group Inc | Construct modular accommodations, Petawawa, Ontario | $896,151 | $208,899 | $896,150 | - |
| 2014/2015 | National Defence | Serbec Inc | Funded Standing offer agreement - General Contractors, Montréal, Quebec | $382,453 | $2,604 | $382,453 | - |
| 2014/2015 | National Defence | Setanta Contracting Ltd | Construct Leopard Power Pack Test Facility, Edmonton, Alberta | $551,398 | $476,673 | $476,673 | - |
| 2014/2015 | National Defence | Setanta Contracting Ltd | Upgrade Mechanical Room HMCS Nonsuch, Edmonton, Alberta | $327,947 | $234,625 | $234,625 | - |
| 2014/2015 | National Defence | Shamrock Building Services Ltd | Basement Insulation, Edmonton, Alberta | $324,235 | $324,235 | $324,235 | - |
| 2014/2015 | National Defence | Sharp Underground Inc | Stormwater Drainage System Upgrade Residential Housing Area, Wainwright, Alberta | $621,318 | $3,000 | $621,318 | - |
| 2014/2015 | National Defence | Shertine Construction Ltd | Design three fighting in built-up areas (FIBUA) buildings, Meaford, Ontario | $1,211,573 | $22,837 | $1,211,573 | - |
| 2014/2015 | National Defence | Siderco Inc Les Entreprises | Recap internal storm sewer for runways 11/29 and 18/36, Saguenay, Quebec | $385,179 | $365,529 | $365,529 | - |
| 2014/2015 | National Defence | Signature Contractors Windsor Inc | Upgrade Main Pool Liner, Cold Lake, Alberta | $264,726 | $257,226 | $257,226 | - |
| 2014/2015 | National Defence | Sikorsky International Operations Inc | Construction of the Maritime helicopter training centre, Shearwater, Nova Scotia | $39,116,806 | $0 | $39,116,806 | - |
| 2014/2015 | National Defence | Silver Birch Contracting Ltd | CFAD Construct Loading Dock, Borden, Ontario | $485,373 | $184,135 | $485,372 | - |
| 2014/2015 | National Defence | Simpson Building Contractors Ltd | Construct New Leopard II Facilities, Gagetown, New Brunswick | $6,157,757 | $205,054 | $205,054 | - |
| 2014/2015 | National Defence | Simpson Building Contractors Ltd | Construction of a Light Weight Towed Howitzer (LWTH) Maintenance Building, Oromocto, New Brunswick | $2,208,699 | $2,185,074 | $2,206,199 | - |
| 2014/2015 | National Defence | Simpson Building Contractors Ltd | Gagetown Military Family Resource Support Centre - Expansion and Renovation, Oromocto, New Brunswick | $2,132,815 | $676 | $2,132,815 | - |
| 2014/2015 | National Defence | Société en Commandite Milican | Longue Pointe supply depot, Longue Pointe, Quebec | $42,660,535 | $1,063,739 | $11,946,937 | - |
| 2014/2015 | National Defence | Stafford Plumbing & Heating Ltd | Heavy Equipment Services - Standing Offer Agreement, Wainwright, Alberta | $330,000 | $9,921 | $46,605 | - |
| 2014/2015 | National Defence | Stint Construction Ltd | Upgrade GRA Fencing, Comox, British Columbia | $257,621 | $232,144 | $232,144 | - |
| 2014/2015 | National Defence | Strong Brothers Heating Air Conditioning and General Contracting Ltd | Install Air Conditioning Building 23, Quinte West, Ontario | $516,565 | $65,759 | $516,565 | - |
| 2014/2015 | National Defence | Strong Brothers Heating Air Conditioning and General Contracting Ltd | Provide Additional Offices B479, Quinte West, Ontario | $324,517 | $324,517 | $324,517 | - |
| 2014/2015 | National Defence | Stuart Olson Constructors | FMF Cape Breton phase IV, Esquimalt, British Columbia | $61,448,714 | $2,904,311 | $61,448,714 | - |
| 2014/2015 | National Defence | TWO D Contracting Ltd | Maintenance and Construction Services, Chilliwack, British Columbia | $800,000 | $27,267 | $413,384 | - |
| 2014/2015 | National Defence | Taurus Contractors Ltd | Denwood House Renovation, Wainwright, Alberta | $296,886 | $216,561 | $216,561 | - |
| 2014/2015 | National Defence | Tect-Hab Inc | Expand swimming pool and bring it into compliance, Saguenay, Quebec | $634,936 | $188,979 | $623,611 | - |
| 2014/2015 | National Defence | TerraEX Inc | Wastewater Treatment Plant Upgrade to Outflow Line & Diffuser, Oromocto, New Brunswick | $2,215,098 | $762,296 | $2,192,394 | - |
| 2014/2015 | National Defence | Three C Contractors Ltd | Explosive Storage Magazines CFAD Bedford - General Contractor, Halifax, Nova Scotia | $14,387,566 | $2,607,078 | $14,309,562 | - |
| 2014/2015 | National Defence | Tipp-Off Inc | Electrical System Upgrades Various Buildings, Edmonton, Alberta | $400,000 | $75,153 | $75,153 | - |
| 2014/2015 | National Defence | Trainor Mechanical Contractors Ltd | Install Fire Protection R01, Suffield, Alberta | $800,605 | $796,055 | $796,055 | - |
| 2014/2015 | National Defence | Transit Paving Inc | Pave R35 Parking Lot, Suffield, Alberta | $282,000 | $282,000 | $282,000 | - |
| 2014/2015 | National Defence | Transport L et R Martel Inc | Project to build a water catchment system, Valcartier, Quebec | $343,691 | $343,691 | $343,691 | - |
| 2014/2015 | National Defence | True Dimensions | Exterior Retrofit R46/A, Shilo, Manitoba | $408,800 | $408,800 | $408,800 | - |
| 2014/2015 | National Defence | True Dimensions | Minor Recap Three R5 Style residential housing units, Shilo, Manitoba | $847,323 | $832,323 | $832,323 | - |
| 2014/2015 | National Defence | True Dimensions | Whole House Renovations YY Style residential housing units, Shilo, Manitoba | $719,577 | $704,577 | $704,577 | - |
| 2014/2015 | National Defence | Turkstra Modular Builders Inc | Purchase of four double wide trailers, Petawawa, Ontario | $419,009 | $387,309 | $387,309 | - |
| 2014/2015 | National Defence | Tyco Integrated Security Canada Inc | Upgrade Intrusion Alarms, Borden, Ontario | $1,894,079 | $4,310 | $1,894,079 | - |
| 2014/2015 | National Defence | UNIBEC Inc Constructions | Recap of roofs B-125, Bagotville, Quebec | $370,587 | $356,360 | $356,360 | - |
| 2014/2015 | National Defence | UTC Fire & Security Canada | Install Intrusion Alarm - Pleasantville Consolidation Project, St John's, Newfoundland and Labrador | $534,070 | $8,535 | $534,070 | - |
| 2014/2015 | National Defence | Universal Sheet Metal Ltd | DY218 - Replace Roofing System, Esquimalt, British Columbia | $599,539 | $0 | $0 | - |
| 2014/2015 | National Defence | Universal Sheet Metal Ltd | Replace Main Roof HVAC Units & Enclosure Walls (Malahat 1), Victoria, British Columbia | $665,438 | $126,804 | $665,438 | - |
| 2014/2015 | National Defence | VCI Controls | Decommission Boiler Upgrade HVAC and Exhaust System, Petawawa, Ontario | $767,286 | $759,286 | $767,286 | - |
| 2014/2015 | National Defence | VCI Controls | Repair various mechanical systems in various buildings, Petawawa, Ontario | $365,570 | $22,553 | $365,570 | - |
| 2014/2015 | National Defence | Vail Civil Contractors Ltd | Sgt Ralph Bridge Design and Replacement, Gagetown, New Brunswick | $3,545,500 | $203,450 | $203,450 | - |
| 2014/2015 | National Defence | Value Master Builders Ltd | Exterior Retrofit residential housing units, Cold Lake, Alberta | $1,996,950 | $1,962,950 | $1,962,950 | - |
| 2014/2015 | National Defence | Varcon Construction Corporation | Construct CFLAWC, Quinte West, Ontario | $37,822,597 | $19,865,613 | $34,315,441 | - |
| 2014/2015 | National Defence | Verity Developments Ltd | Site Adapt Design/Construction - New Barrier Free Transitional Accommodations, Victoria, British Columbia | $1,105,550 | $204,689 | $1,105,550 | - |
| 2014/2015 | National Defence | Vic's Group Inc | CFC Site Drainage, Toronto, Ontario | $2,021,188 | $1,731,403 | $1,731,403 | - |
| 2014/2015 | National Defence | Wade General Contracting Ltd | Construction of Modular Housing Phase II, Petawawa, Ontario | $8,860,114 | $7,545,836 | $8,727,299 | - |
| 2014/2015 | National Defence | Wade General Contracting Ltd | Recaps on residential housing units, Petawawa, Ontario | $1,373,850 | $1,356,040 | $1,356,040 | - |
| 2014/2015 | National Defence | Wade General Contracting Ltd | Upgrade Various Underground Tanks, Petawawa, Ontario | $1,072,910 | $8,112 | $1,072,910 | - |
| 2014/2015 | National Defence | Wahl Construction Ltd | Construction test facility, Suffield, Alberta | $5,524,747 | $2,376,273 | $5,524,747 | - |
| 2014/2015 | National Defence | Wahl Construction Ltd | Standing offer agreement - DRDC General Construction, Suffield, Alberta | $302,157 | $0 | $302,157 | - |
| 2014/2015 | National Defence | Waterdon Construction Ltd | Multi Option Simulation Compound, Ottawa, Ontario | $731,532 | $576,532 | $731,532 | - |
| 2014/2015 | National Defence | Waterdon Construction Ltd | Two Storey Administrative Building, Ottawa, Ontario | $709,757 | $709,757 | $709,757 | - |
| 2014/2015 | National Defence | Webster Electric Ltd | Replace Switch Gear RAPPRI (Winchelsea Island and Fairwinds), Esquimalt, British Columbia | $427,985 | $129,810 | $129,810 | - |
| 2014/2015 | National Defence | Western Weather Protector Ltd | Replace Roof Building 187, Edmonton, Alberta | $498,569 | $498,569 | $498,569 | - |
| 2014/2015 | National Defence | Westridge Construction Ltd | Upgrade Gable-End Walls Regina Armoury, Regina, Saskatchewan | $489,287 | $489,287 | $489,287 | - |
| 2014/2015 | National Defence | Williams Scotsman of Canada Inc | Lease of Modular Trailer Complex, Chilliwack, British Columbia | $1,482,222 | $19,389 | $1,482,222 | - |
| 2014/2015 | National Defence | Williams Scotsman of Canada Inc | Provision of Temporary Building Royal Military College RMC#60, Kingston, Ontario | $314,302 | $17,000 | $271,902 | - |
| 2014/2015 | National Defence | Wilson Builders Ltd | Foundation Digs CFHA, Gagetown, New Brunswick | $617,863 | $617,863 | $617,863 | - |
| 2014/2015 | National Defence | XL Electric Limited | Jetty NA Upgrade Shore Power, Halifax, Nova Scotia | $532,676 | $461,000 | $461,000 | - |
| 2014/2015 | National Defence | XL Electric Limited | Shearwater tunnel upgrade (electrical system/ lights/ plugs/ panels), Halifax, Nova Scotia | $480,890 | $204,463 | $204,463 | - |
| 2014/2015 | National Defence | Électrique M J L Inc | Replace elements of the electrical distribution system of several buildings and of the primary network, Saint-Jean-sur-Richelieu, Quebec | $318,640 | $24,584 | $318,640 | - |
| 2014/2015 | National Defence | Équipements Claude Pedneault Inc | Renovate fuel farm loading/unloading area, Saguenay, Quebec | $1,205,861 | $28,388 | $1,205,861 | - |
| 2014/2015 | Natural Resources | Contracts under $250,000 and cost plus contracts of less than $25,000 (8 contractors) | Total | $0 | $380,948 | $0 | - |
| 2014/2015 | Natural Resources | Contracts under $250,000 and costs plus contracts under $25,000 (12 contractors) | Total | $0 | $761,497 | $0 | - |
| 2014/2015 | Natural Resources | Public Works and Government Services Canada | Fit-Up, Centre 10, Calgary, Alberta | $709,835 | $709,835 | $709,835 | - |
| 2014/2015 | Natural Resources | Sanagatiit Construction Ltd | New facilities, Resolute, Nunavut | $18,895,385 | $30,822 | $17,548,189 | - |
| 2014/2015 | Office of Infrastructure of Canada | Angeles Lopez Gutierrez in Trust | Acquisition of property for the new bridge for the St. Lawrence Corridor, Saint-Laurent, Quebec | $738,356 | $738,356 | $738,356 | - |
| 2014/2015 | Office of Infrastructure of Canada | Angie Pelonis Notaire Inc in Trust | Acquisition of property for the new bridge for the St. Lawrence Corridor, Saint-Laurent, Quebec | $393,958 | $393,958 | $393,958 | - |
| 2014/2015 | Office of Infrastructure of Canada | Contracts under $250,000 and cost plus contracts under $25,000 (3 contractors) | Total | $0 | $395,561 | $0 | - |
| 2014/2015 | Office of Infrastructure of Canada | Francois Loiselle Notaire in Trust | Acquisition of property for the new bridge for the St. Lawrence Corridor, Saint-Laurent, Quebec | $557,611 | $1,840,423 | $557,611 | - |
| 2014/2015 | Office of Infrastructure of Canada | Michelle Tremblay Notaire Inc in Trust | Acquisition of property for the new bridge for the St. Lawrence Corridor, Saint-Laurent, Quebec | $779,621 | $3,404,487 | $779,621 | - |
| 2014/2015 | Office of Infrastructure of Canada | Prud'homme Fontaine Dolan S E N C R L in Trust | Acquisition of property for the new bridge for the St. Lawrence Corridor, Saint-Laurent, Quebec | $676,937 | $2,979,344 | $676,937 | - |
| 2014/2015 | Office of Infrastructure of Canada | Sherry Ao in Trust | Acquisition of property for the new bridge for the St. Lawrence Corridor, Saint-Laurent, Quebec | $450,526 | $450,526 | $450,526 | - |
| 2014/2015 | Privy Council Office | Contracts under $250,000 and cost plus contracts under $25,000 (5 contractors) | Total | $0 | $61,622 | $0 | - |
| 2014/2015 | Privy Council Office | Multivesco Inc | Leasehold improvements initial fit-up of 30 Victoria, Gatineau, Quebec | $1,729,891 | $0 | $1,583,822 | - |
| 2014/2015 | Privy Council Office | Public Works and Government Services Canada | Leasehold Improvement - 30 Victoria, Gatineau, Québec | $12,715,857 | $249,759 | $10,603,064 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 152610 Canada Inc | Kitchen redevelopment at Millhaven Institution, Bath, Ontario | $4,349,980 | $747,023 | $4,331,585 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 152610 Canada Inc | New fire storage water reservoir and pumping station, Bath, Ontario | $3,007,646 | $1,197,043 | $2,983,342 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 1622294 Ontario Inc | Central heating plant modifications, Kingston, Ontario | $2,982,635 | $2,294,823 | $2,294,823 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 2015168 Ontario Inc | Cornwall lease, Cornwall, Ontario | $9,834,623 | $400,387 | $1,138,561 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 2099042 Ontario Limited | Repair storm and sanitary lines, Kingston, Ontario | $2,212,206 | $3,000 | $2,212,206 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 5226 Nunavut Ltd | Duplex construction, Rankin Inlet, Nunavut | $1,174,688 | $255,188 | $1,174,688 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 5226 Nunavut Ltd | RCMP modular homes, Resolute Bay, Nunavut | $1,264,850 | $0 | $1,264,850 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | 995451 Ontario Inc | Heating plant at Kingston Institution, Kingston, Ontario | $505,544 | $500,625 | $500,625 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ainsworth Inc | Connect building 27 to combine heat and power service at Springhill Institution, Springhill, Nova Scotia | $325,144 | $11,589 | $325,144 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Applied Electronics Ltd | Purchase and installation of audio/visual equipment, Regina, Saskatchewan | $1,286,185 | $1,286,185 | $1,286,185 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Associated Engineering Ltd | Preliminary work 7 ports of entry, Various locations, Various provinces | $820,593 | $473,734 | $820,593 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Atlantica Mechanical Contractors Inc | Boiler plant upgrade at Dorchester Institution, Dorchester, New Brunswick | $1,270,489 | $872,479 | $872,479 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Avondale Construction Limited | Corcan multipurpose buildings Westmorland and Dorchester Institutions, Dorchester, New Brunswick | $3,657,836 | $0 | $3,657,836 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Avondale Construction Limited | Generic support buildings, Springhill, Nova Scotia and Renous, New Brunswick | $7,563,106 | $0 | $7,563,106 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | BECC Construction Group Ltd | 50 bed living units, Gravenhurst, Ontario | $7,150,217 | $2,797,977 | $6,279,579 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | BECC Construction Group Ltd | Finance and parole hearing building, Gravenhurst, Ontario | $2,494,100 | $346,407 | $2,494,100 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | BECC Construction Group Ltd | New Great Lakes Marine Security Operations Centre construction, Niagara, Ontario | $11,177,142 | $2,600,064 | $11,177,142 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Bervin Construction Ltd | Generic support buildings GI/GO at Pacific Institution Regional Treatment Centre and Matsqui Institution, Abbotsford, British Columbia | $5,362,853 | $56,281 | $5,362,853 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Bervin Construction Ltd | Non cell window upgrade, Agassiz, British Columbia | $254,132 | $0 | $254,132 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Bervin Construction Ltd | Parole office relocation, Abbotsford, British Columbia | $2,749,246 | $24,897 | $2,749,246 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Beton Mobile St-Alphonse Inc | Parking lot expansion, St-Jean, Quebec | $320,870 | $320,170 | $320,170 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Birch Hill Construction Ltd | Parking lot expansion at Springhill Institution, Springhill, Nova Scotia | $1,761,080 | $0 | $1,759,579 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Bird Construction Company | 96 beds unit at Mission Institution, Mission, British Columbia | $11,185,560 | $0 | $11,185,560 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Bona Building and Management Co Ltd | Building consolidation, Ottawa, Ontario | $1,123,706 | $1,123,706 | $1,123,706 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Bondfield Construction Company Limited | New medium security housing units, Kingston, Ontario | $22,611,297 | $421,304 | $22,601,346 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CBCI Telecom | Fit-up - Consolidation Project, Toronto, Ontario | $300,000 | $256,684 | $256,684 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CCR Construction Ltd | Preliminary work 7 ports of entry, Various locations, Various provinces | $5,414,045 | $3,874,388 | $4,326,638 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | 20 living units Fraser Valley Institution, Abbotsford, British Columbia | $4,049,219 | $362,301 | $4,049,219 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Bath and Millhaven Institutions temporary kitchen, Bath, Ontario | $690,242 | $0 | $690,242 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Building range construction, Sainte-Anne-des-Plaines, Quebec | $731,608 | $228,330 | $715,688 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Dust collection system upgrade, Springhill, Nova Scotia | $795,567 | $62,572 | $795,567 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Enlargment of peepholes in the cell doors at Archambault Institution, Sainte-Anne-des-Plaines, Quebec | $975,881 | $118,221 | $118,221 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Phoenix Unit renovations at Collins Bay Institution, Kingston, Ontario | $446,002 | $446,002 | $446,002 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Replacement of the steam line of well #5 at Federal Training Centre, Laval, Quebec | $550,000 | $375,000 | $375,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Retrofit and expansion of Joyceville Institution admissions and discharges, Kingston, Ontario | $253,088 | $0 | $253,088 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Retrofit of EVI Building C-29 admissions and discharge, Kingston, Ontario | $336,260 | $9,974 | $336,260 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Retrofit of Joyceville Medium Institution broad based area to an assessment area, Kingston, Ontario | $375,220 | $245,588 | $375,220 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Retrofit of a metal shop at Federal Training Centre, Laval, Quebec | $483,065 | $483,065 | $483,065 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Store relocation at Archambault Institution, Sainte-Anne-des-Plaines, Quebec | $291,154 | $246,154 | $246,154 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Structural repair, Springhill, Nova Scotia | $344,903 | $70,000 | $344,903 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | CORCAN | Structural repairs of Block C at Westmorland Institution, Dorchester, New Brunswick | $293,316 | $293,316 | $293,316 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Calgary International Airport Authority | New international airport, Calgary, Alberta | $1,571,608 | $659,776 | $1,571,608 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Can-Tec Drafting Services Ltd | Architecture and engineering services for new detachment, Island Lake, Manitoba | $407,000 | $109,700 | $254,001 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Canada Post Corporation | Canada Post Corporation modernization, Vancouver, British Columbia | $6,000,000 | $0 | $4,787,128 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Castle Rock Construction | Construction of new government of Canada building for RCMP Forensic Identification Services, Moncton, New Brunswick | $3,072,908 | $2,121,833 | $2,121,833 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Castle Rock Construction Services Inc | Firing range reconstruction at Atlantic Institution, Renous, New Brunswick | $1,833,046 | $1,461,063 | $1,461,063 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Chase Office Interiors Inc | Building consolidation, Vancouver, British Columbia | $272,189 | $0 | $272,189 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Consoltec Inc | Construction of a building, Cowansville, Quebec | $2,660,567 | $293,247 | $2,660,567 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Consoltec Inc | Housing unit at Montée St-François Institution, Laval, Quebec | $6,614,674 | $42,640 | $6,614,238 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Construction Cybco Inc | 96 bed living units construction, Laval, Quebec | $11,703,197 | $563,663 | $11,657,617 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Construction Cybco Inc | Project realization road demolishing and new entry and security equipment, Laval, Quebec | $9,674,572 | $0 | $9,674,572 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Construction D L T Inc | Roof replacement and exterior corridors, Cowansville, Quebec | $1,035,632 | $23,404 | $1,035,632 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Construction Giron Inc | Institution kitchen renovation, Cowansville, Quebec | $1,536,938 | $51,108 | $1,536,938 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Construction Ondel | New electric generator at Saint-Anne-des-Plaines establishment, Saint-Anne-des-Plaines, Quebec | $4,177,701 | $0 | $4,177,701 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Construction Socam Ltée | Expansion of the institution, Joliette, Quebec | $7,274,683 | $4,487,298 | $7,216,458 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Continental Casualty Company | Fort Walsh cadet accommodation building, Regina, Saskatchewan | $24,773,048 | $13,679,750 | $23,005,915 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Contracts under $250,000 and cost plus contracts under $25,000 (1 contractor)** | Total | $0 | $138,472 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Contracts under $250,000 and cost plus contracts under $25,000 (234 contractors) | Total | $0 | $7,429,920 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Contracts under $250,000 and cost plus contracts under $25,000 (281 contractors) | Total | $0 | $64,177,651 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Contracts under $250,000 and cost plus contracts under $25,000 (6 contractors) | Total | $0 | $541,117 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Contracts under $250,000 and cost plus contracts under $25,0000 (102 contractors) | Total | $0 | $19,006,011 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Correctional Service of Canada | 7 ports of entry modular base, Various locations, Various provinces | $8,002,881 | $5,184,792 | $5,957,440 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Correctional Service of Canada | Second temporary port of entry, Cornwall, Ontario | $492,720 | $0 | $492,720 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | D R Garrett Construction Ltd | Replacement of toilets and lavatories at Kent Institution, Agassiz, British Columbia | $60,000 | $0 | $60,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | D R Garrett Construction Ltd | Replacement of toilets, Agassiz, British Columbia | $630,432 | $0 | $630,432 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | DMH Equities Ltd | Warehouse consolidation, Vancouver, British Columbia | $754,480 | $754,480 | $754,480 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | DSRA Architecture Inc | Architecture and engineering services for new detachment, Ingonish Beach, Nova Scotia | $324,800 | $231,765 | $289,823 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | DSRA Architecture Inc | Consulting services, Twillingate, Newfoundland and Labrador | $329,589 | $329,589 | $329,589 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Dalren Limited | Warkworth Institution inner perimeter lighting enhancement, Campbellford, Ontario | $927,425 | $768,546 | $790,096 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Delco Automation Inc | Security electronics for door controls, Various locations, Saskatchewan | $313,875 | $265,325 | $265,325 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Delco Automation Inc | Supply and install and provide operational and training on closed circuit television equipment, Various locations, Ontario | $1,214,150 | $145,069 | $1,214,150 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Delco Automation Inc | Supply and install on range closed circuit television equipment in Ontario region medium institutions, Various locations, Ontario | $2,233,838 | $0 | $2,233,838 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Dig'n Dirt Ltd | New parking lot extension, Bath, Ontario | $579,371 | $579,371 | $579,371 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Donald A Giddings Law Corporation | Acquire residence, Dease Lake, British Columbia | $255,371 | $255,371 | $255,371 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Dorbec Construction Inc | Repair of Hochelaga Community Correctional Centre, Montréal, Quebec | $729,000 | $453,661 | $453,661 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Dowland Contracting Ltd | 96 bed living units at Drumheller Institution, Drumheller, Alberta | $12,335,411 | $3,181,294 | $12,110,330 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Dundeal Summer 2011 Collection (GP)Inc | Fit-up - Consolidation Project, Toronto, Ontario | $1,143,102 | $1,024,363 | $1,024,363 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | EBC Inc | Construction of two housing units at the institution, Cowansville, Quebec | $19,867,676 | $557,454 | $19,825,937 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | EXP Architects Inc | Bible Hill expansion project, Bible Hill, Nova Scotia | $380,000 | $57,612 | $57,612 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | EXP Architects Inc | Design of detachment, St-Leonard, New Brunswick | $788,177 | $0 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | EXP Architects Inc | Detachment design services, Bible Hill, Nova Scotia | $386,411 | $386,411 | $386,411 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Elite Construction Inc | 50 bed living units at Frontenac Institution, Kingston, Ontario | $7,911,442 | $1,250,201 | $7,604,665 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Elite Construction Inc | CBI front entrace renovations Kingston Institution, Kingston, Ontario | $627,400 | $0 | $627,400 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Elite Construction Inc | Hospital Building S upgrade, Bath, Ontario | $1,006,354 | $0 | $1,006,354 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Elite Construction Inc | New maximum security housing unit, Kingston, Ontario | $18,080,270 | $760,651 | $18,080,270 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Elmara Construction Co Ltd | Warkworth Institution fire alarm system upgrades, Campbellford, Ontario | $2,551,872 | $627,887 | $2,295,157 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Elmara Construction Co Ltd | Warkworth Institution underground duct replacement, Campbellford, Ontario | $909,061 | $837,966 | $889,466 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Emmons & Mitchell Construction | New recreation yard, Kingston, Ontario | $1,019,801 | $0 | $1,019,801 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | FSC Inc | Purchase and installation of security system, Various locations, Various provinces | $259,853 | $34,344 | $259,852 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Federal Bridge Corporation Ltd | Second temporary port of entry, Cornwall, Ontario | $12,800,000 | $229,133 | $12,196,512 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ferguson Electric Company Ltd | Millhaven Institution electrical distribution system upgrade, Bath, Ontario | $670,110 | $610,210 | $670,110 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Fort McMurray Airport Authority | Airport expansion, Fort McMurray, Alberta | $571,097 | $26,861 | $571,097 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Foulem Construction Ltée | 50 bed living units at Dorchester Institution, Westmorland, New Brunswick | $6,888,788 | $22,407 | $6,888,788 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Gerry Enns Contracting Ltd | Kitchen retrofit at Matsqui Institution, Abbotsford, British Columbia | $4,492,860 | $2,833,995 | $4,395,389 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Glenco Electric Ltd | M3 cell call & GFCI upgrade at Matsqui Institution, Abbotsford, British Columbia | $2,999,885 | $0 | $2,999,885 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Glenview Construction Ltd | Building consolidation, Ottawa, Ontario | $908,300 | $908,300 | $908,300 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Graham Construction and Engineering Inc | 96 bed maximum living units at Stony Mountain Institution, Winnipeg, Manitoba | $21,638,225 | $75,700 | $21,638,225 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Graham Construction and Engineering Inc | Building C-5 sloped roof upgrades at Stony Mountain Institution, Winnipeg, Manitoba | $676,249 | $270,700 | $270,700 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Graham Construction and Engineering Inc | Gymasium and vocational areas at Willow Cree Healing Centre, Duck Lake, Saskatchewan | $6,375,028 | $2,026,723 | $2,026,723 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Graham Construction and Engineering Inc | SMI, Building C-5 roof upgrades (clerestory windows) at Stony Mountain Institution, Winnipeg, Manitoba | $335,800 | $0 | $335,800 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Graham Design Builders Inc | Construction of generic support building GI at Stony Mountain Institution, Winnipeg, Manitoba | $12,021,891 | $4,068 | $12,021,891 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Greyback Construction Ltd | Construction of building, Anahim Lake, British Columbia | $7,082,276 | $160,625 | $160,625 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Groupe Geyser Inc | Expansion of the institution, Joliette, Quebec | $3,638,009 | $0 | $3,638,009 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Groupe Piché Construction Inc | Construction of a new building, Municipalité de La Macaza, Quebec | $3,805,448 | $270,217 | $3,805,448 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Gus Poirier Construction Ltd | Detachment construction, Fraser Lake, British Columbia | $2,391,578 | $0 | $2,391,578 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Haworth Ltd | Building consolidation, Vancouver, British Columbia | $520,880 | $0 | $520,880 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Haworth Ltd | New Great Lakes Marine Security Operations Centre construction, Niagara, Ontario | $272,411 | $16,420 | $272,411 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | IBI/HB Group | Architecture and engineering services for new detachment, Anahim Lake, British Columbia | $339,500 | $9,000 | $339,137 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Industrial Electrical Contractors Ltd | Transformer replacement at Milhaven Institution, Bath, Ontario | $284,318 | $284,318 | $284,318 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | J Raymond Couvreur et Fils Inc | Roof repair at Sainte-Anne-des-Plaines Institution, Sainte-Anne-des-Plaines, Quebec | $2,157,803 | $680,937 | $680,937 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | JC Sulphur Construction Ltd | Construction at TPOF, Ottawa, Ontario | $5,445,396 | $4,103,926 | $4,725,409 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | James Johnson Enterprises Ltd Chilliwack | MCCP upgrade/new CER room at Kent Institution, Agassiz, British Columbia | $721,874 | $0 | $721,874 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | James Johnson Enterprises Ltd Chilliwack | South mechanical room chiller upgrade at Kent Institution, Agassiz, British Columbia | $253,987 | $0 | $253,987 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | James McIntyre Law Corporation | Purchase of land, Aldergrove, British Columbia | $395,000 | $0 | $395,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Jeffrey G Wallans Construction Ltd | CORCAN workshop addition, Bath, Ontario | $2,213,851 | $0 | $2,213,851 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Jeffrey G Wallans Construction Ltd | Provision of new sprinklers, Kingston, Ontario | $681,321 | $0 | $681,321 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Johnson Control Canada Inc | Preliminary work 7 ports of entry, Various locations, Various provinces | $348,110 | $348,110 | $348,110 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Joneljim Concrete Construction | Detachment construction, Ingonish, Nova Scotia | $4,433,482 | $1,266,293 | $1,266,293 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Kadam Developments Ltd | Transportable cell facility, Deschambault Lake, Saskatchewan | $372,800 | $372,800 | $372,800 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Kadam Developments Ltd | Transportable cell facility, Onion Lake, Saskatchewan | $298,052 | $14,393 | $298,052 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Karwood Estates | Purchase property, Whiteborne, Newfoundland and Labrador | $421,778 | $421,778 | $421,778 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Kinetic Construction Ltd | WHI - waste water treatment plant phase 2, Metchosin, British Columbia | $940,999 | $11,999 | $940,999 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | L & R Construction Limited | 14 bed living units, Truro, Nova Scotia | $3,632,262 | $803,550 | $3,577,984 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | LEC Engineering Contracting Ltd | 50 bed living units at Ferndale Institution, Mission, British Columbia | $5,898,786 | $474,723 | $5,865,431 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | LK Industries Inc | Roof repair of the Building M1 at La Macaza Institution, La Macaza, Quebec | $372,570 | $301,712 | $301,712 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Landmark Municipal Services ULC | Joyceville Institution water tower upgrades and repair, Kingston, Ontario | $1,549,254 | $336,669 | $652,586 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Lark Projects Limited | Port replacement, Aldergrove, British Columbia | $17,893,285 | $8,126,093 | $8,126,093 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Laurin Group | Construction of training facility, Ottawa, Ontario | $1,280,897 | $28,443 | $1,280,896 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Le Goupe Drumco Construction Inc | Morses border crossing replacement, Saint-Armand, Quebec | $1,030,629 | $1,030,629 | $1,030,629 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Le Groupe Cevec Inc | Refridgeration units replacement at Drummond Institution, Drummondville, Quebec | $427,702 | $420,177 | $420,177 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Lear Construction Management Ltd | 96 bed living units at Bowden Institution, Innisfail, Alberta | $13,262,760 | $655,446 | $12,486,852 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Les Constructions Lavacon Inc | New dwelling units Sainte-Anne-des-Plaines Institution, Sainte-Anne-des-Plaines, Quebec | $6,845,713 | $198,494 | $6,682,399 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Limen Group Ltd | Collins Bay Institution renovation and repairs to concrete security walls, Kingston, Ontario | $4,199,441 | $61,356 | $4,122,997 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Lys Air Mécanic Inc | Ventilation system - chlorine room and pumping station at Archambault Institution, Sainte-Anne-des-Plaines, Quebec | $253,628 | $253,628 | $253,628 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | M Sullivan & Son Ltd | Generic support buildings, Kingston, Ontario | $28,212,594 | $111,495 | $28,212,594 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | MPM Construction Services Ltd | Depot redevelopment D block, Regina, Saskatchewan | $555,424 | $163,923 | $555,424 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maclachlin McNab Hembroff | Acquisition of new subdivision, Coaldale, Alberta | $1,599,348 | $1,599,348 | $1,599,348 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Macson Development Ltd | Canada Place fit up, Edmonton, Alberta | $2,113,886 | $0 | $2,113,886 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maple-Reinders Inc | 96 bed living units at Edmonton Maximum Security Institution, Edmonton, Alberta | $20,937,212 | $1,755,096 | $20,915,574 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maple-Reinders Inc | Generic support building Edmonton Maximum Security Institution, Edmonton, Alberta | $7,382,683 | $65,881 | $7,382,683 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maram Building Corp | Fenbrook Institution fire range and training building, Gravenhurst, Ontario | $2,920,833 | $48,515 | $2,920,833 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Marcomm Systems Group | Supply and install closed circuit television monitoring and guard tour systems, Various locations, Saskatchewan | $375,457 | $254,338 | $254,338 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Marcomm Systems Group | Supply and install on range closed circuit television equipment in Prairie region medium institutions, Various locations, Manitoba | $10,179,726 | $264,275 | $10,179,726 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Marcomm Systems Group | Supply and install on range closed circuit television equipment in Quebec region medium institutions, Various locations, Quebec | $6,319,200 | $611,036 | $6,319,200 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maskimo Construction Inc | Repair roads and parking lot, Sainte-Anne-des-Plaines, Quebec | $5,018,915 | $0 | $4,004,306 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maxim 2000 Inc | New food services building, Dorchester, New Brunswick | $5,240,655 | $4,808,180 | $5,009,850 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Maxim 2000 Inc | New living units, Springhill, Nova Scotia | $22,334,124 | $772,763 | $22,263,601 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Modern Niagara Toronto Inc | Boiler installation at Beaver Creek Institution, Gravenhurst, Ontario | $272,586 | $272,586 | $272,586 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | NORR Limited | Architecture and engineering services for armoury expansion, Ottawa, Ontario | $649,697 | $96,499 | $622,747 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Neveu & Neveu Ltée | Heating plant boiler replacement at Joliette Institution, Joliette, Quebec | $278,215 | $180,898 | $180,898 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Newton Enterprises | Construction detachment, Island Lake, Manitoba | $6,964,375 | $3,726,024 | $3,726,024 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Niacon Limited | Range upgrades E Unit, Bath, Ontario | $3,140,056 | $15,450 | $975,856 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Nor-Tec Electic Ltd | Inmate housing building communications upgrade Rockwood Institution Stony Mountain, Winnipeg, Manitoba | $467,888 | $0 | $467,888 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Number Ten Architectural Group | Architecture and engineering services for new detachment, 100 Mile House, British Columbia | $309,026 | $202,048 | $292,628 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Onni Main 2009 Development Limited Partnership | Building consolidation, Vancouver, British Columbia | $1,550,378 | $0 | $1,550,378 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Onni Main 2009 Development Limited Partnership | Vancouver Metro project, Vancouver, British Columbia | $317,355 | $18,754 | $317,355 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | P3A Architects Ltd | Depot redevelopment tunnels, Regina, Saskatchewan | $916,314 | $637,002 | $637,002 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | PCL Constructors Canada Inc | Detachment construction, Gypsumville, Manitoba | $4,150,451 | $3,057,629 | $4,044,271 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | PM Contracting Ltd | Grand Valley Institution new 2-storey building, Kitchener, Ontario | $5,656,692 | $3,385,735 | $4,003,491 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Parkin Architects Ltd | Architecture and engineering services for new detachment, Arviat, Nunavut | $619,340 | $247,252 | $247,252 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Parthian Mechanical Inc | Central heating plant boiler replacement, Joyceville, Ontario | $535,365 | $0 | $535,365 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Penn-Co Construction Canada 2003 Ltd | New detachment, Maidstone, Saskatchewan | $5,843,483 | $0 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Penn-co Construction Management Ltd | Doubling-up 3 ports replacement, Various locations, Manitoba | $14,944,266 | $0 | $14,899,708 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Piche Bros Contracting Inc | Construction of fourplex accommodation, Wollaston Lake, Saskatchewan | $1,415,454 | $1,415,454 | $1,415,454 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Piche Bros Contracting Inc | Detachment construction, Manning, Alberta | $4,436,453 | $493,428 | $4,436,453 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Pomerleau Inc | Construction of new housing units maximum security, Donnacona, Quebec | $21,212,198 | $210,263 | $21,212,198 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Pomerleau Inc | New maximum security housing unit, Renous, New Brunswick | $21,819,066 | $1,715,580 | $21,130,149 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Prism Construction Inc | Renovation of first floor Government of Canada building for CSC, Moncton, New Brunswick | $400,758 | $103,614 | $103,614 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Prism Construction Inc | Segregation door replacement, Dorchester, New Brunswick | $456,969 | $0 | $456,969 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Provencher Roy et Associés architectes | Commercial expansion project, Lacolle, Quebec | $610,211 | $156,467 | $610,211 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Quad Pro Construction Inc | Maximum security cell unit, Kingston, Ontario | $20,039,738 | $2,838,535 | $19,804,613 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Quinan Construction Ltd | Fenbrook Institution Buildings CEFG renovation showers and baseboards, Gravenhurst, Ontario | $3,947,597 | $1,280,000 | $3,479,845 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Quinan Construction Ltd | Fenbrook Institution kitchen redesign and modifications to Building D, Gravenhurst, Ontario | $470,931 | $0 | $470,931 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Quorex Construction | Depot redevelopment B block, Regina, Saskatchewan | $7,815,534 | $7,120,476 | $6,525,058 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Quorex Construction | Renovations D block fourth floor, Regina, Saskatchewan | $572,900 | $572,900 | $572,900 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Quorex Construction | Renovations D block second floor, Regina, Saskatchewan | $584,792 | $584,792 | $584,792 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | RBM Architecture Inc | Architecture and engineering services for new detachment, Grande Cache, Alberta | $345,801 | $0 | $328,932 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ram Mechanical Ltd | Mission living unit heating infrastructure project, Mission, British Columbia | $1,215,000 | $0 | $1,215,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Randall Plumbing and Heating Limited | Powerhouse deaerator tank and feedwater pumps replacement for Rockwood and Stony Mountain Institutions, Winnipeg, Manitoba | $406,573 | $0 | $406,573 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Raoul Beaulieu Inc | Replacement of cooler 1 and 3 at Donnacona Institution, Donnacona, Quebec | $976,600 | $938,214 | $938,214 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Rebanks Pepper Littlewood Architects | Architecture and engineering services for the New Great Lakes Marine Security Operations Centre, Niagara, Ontario | $1,719,375 | $452,456 | $1,629,309 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Roche Construction Inc | Construction of a building at the Federal Training Centre, Laval, Quebec | $2,519,938 | $96,828 | $2,519,938 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ross Clair (ROM) Contractors | Construct new building at Grand Valley Institution, Kitchener, Ontario | $5,462,257 | $143,089 | $5,462,257 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ross Clair (ROM) Contractors | Construction of new Portsmouth Community Correction Centre, Kingston, Ontario | $6,570,251 | $7,772 | $6,570,251 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ross Clair (ROM) Contractors | Kitchen renovation, Kingston, Ontario | $6,481,050 | $1,954,752 | $5,543,973 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Ross Clair (ROM) Contractors | Range upgrades A Unit, Bath, Ontario | $3,769,792 | $0 | $3,769,792 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SEPW Architecture Inc | Architecture and engineering services for new detachment and housing, Black Lake, Saskatchewan | $746,077 | $546,458 | $546,458 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SEPW Architecture Inc | Architecture and engineering services for new detachment, Ahtahkakoop, Saskatchewan | $537,556 | $27,866 | $27,866 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SEPW Architecture Inc | Architecture and engineering services for new detachment, Maidstone, Saskatchewan | $495,000 | $329,175 | $391,050 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SEPW Architecture Inc | Architecture and engineering services for new detachment, Onion Lake, Saskatchewan | $495,000 | $69,300 | $69,300 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SEPW Architecture Inc | Depot redevelopment B block, Regina, Saskatchewan | $1,027,557 | $224,413 | $977,495 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC Lavalin Operations & Maintenance Inc | Betterments to various buildings, Various locations, Ontario | $183,580 | $37,204 | $183,580 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC Lavalin Operations & Maintenance Inc | Betterments to various buildings, Various locations, Various Provinces | $8,222,028 | $6,269,504 | $6,269,504 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC-Lavalin | Installation of access control system to residence rooms in training center, Rigaud, Quebec | $1,874,147 | $212,242 | $1,874,147 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC-Lavalin | Redevelopment of entrance to classrooms and offices, Rigaud, Quebec | $627,244 | $0 | $590,268 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC-Lavalin Inc | Building consolidation, Winnipeg, Manitoba | $270,811 | $0 | $270,811 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC-Lavalin O&M Inc | Betterments to various buildings, Various locations, Ontario | $18,583 | $18,583 | $18,583 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC-Lavalin Operations & Maintenance Inc | Laboratory fit up project, Ottawa, Ontario | $341,125 | $0 | $341,125 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SNC-Lavalin Operations & Maintenance Inc | Second temporary port of entry, Cornwall, Ontario | $314,401 | $0 | $314,401 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | SPD Construction Ltd | Detachment construction, Port Simpson, British Columbia | $1,714,902 | $0 | $1,714,902 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Seagate Construction | New programs food services spiritual buildings, Truro, Nova Scotia | $5,215,111 | $2,819,533 | $4,902,988 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Senstar Stellar Corporation | Replacement of the existing federal digital system, Various locations, Alberta | $471,382 | $0 | $471,382 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Senstar Stellar Corporation | Upgrade of the personal alarm locating systems at nine correctional facilities, Various locations, Ontario | $1,682,285 | $85,351 | $1,399,589 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Shared Services Canada | Building consolidation, Ottawa, Ontario | $886,975 | $886,975 | $886,975 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Shunda Consulting and Construction | New training and storage building, Innisfail, Alberta | $447,885 | $447,885 | $447,885 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Simmchen Construction Ltd | Cell upgrades Shepody Healing Centre, Dorchester, New Brunswick | $491,860 | $57,878 | $491,860 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | St-Gelais Montminy & Associés Architectes | Border crossing modernization project, Lacolle, Quebec | $643,674 | $643,674 | $643,674 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stantec Architecture Ltd | Architecture and engineering services for new detachment, Tofino, British Columbia | $392,336 | $53,000 | $53,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stantec Architecture Ltd | Design and construction, Elk Point, Alberta | $436,626 | $40,000 | $40,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stantec Architecture Ltd | Design of detachment, Shawinigan Lake, British Columbia | $333,221 | $25,000 | $25,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stantec Architecture Ltd | Pleasant Camp border crossing redevelopment, Stikine, British Columbia | $250,886 | $250,886 | $250,886 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stantec Consulting Ltd | Architecture and engineering services for roof system, Regina, Saskatchewan | $515,821 | $13,579 | $13,579 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stantec Consulting Ltd | Design of multiple detachements, Regina, Saskatchewan | $475,269 | $0 | $0 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Stephens Kozak Architects Ltd | Architecture and engineering services for new detachment, Manning, Alberta | $323,220 | $15,800 | $313,720 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Summit Brooke Construction | Detachment construction, 100 Mile House, British Columbia | $5,530,366 | $4,502,122 | $5,317,385 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Sutherland Excavating Ltd | Waste water treatment plant debris removal system at Renous parole office, Renous, New Brunswick | $858,390 | $2,639 | $858,390 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | TNT Lawyers Ltd | Purchase of land, Aldergrove, British Columbia | $309,624 | $0 | $309,624 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Taurus Contractors Ltd | Detachment cell retrofit, Ulukhaktok, Northwest Territories | $745,651 | $143,571 | $745,651 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Trainor Mechanical Contractors Ltd | Fire system upgrade, Innisfail, Alberta | $897,785 | $0 | $897,785 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Tri City Canada Inc | 5 bed units at Rockwood, Stony Mountain, Manitoba | $8,821,434 | $890,910 | $8,821,434 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Tri City Canada Inc | Detachment construction, Grande Cache, Alberta | $4,819,656 | $424,409 | $4,819,656 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Tri City Canada Inc | Edmonton Institution for Women principal entrance and industries building construction, Edmonton, Alberta | $15,601,072 | $7,000,000 | $8,031,300 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | UPA Concept a Joint Venture | Bowden (mininum) expansion, Innisfail, Alberta | $13,997,138 | $5,399,827 | $13,997,138 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | UPA Concept a Joint Venture | Willow Cree Healing Lodge expansion, Duck Lake, Saskatchewan | $4,724,288 | $0 | $4,724,288 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | UPA Construction Group (AB) Ltd | 5 bed units at Riverbend Minimum Security Institution, Prince Albert, Saskatchewan | $8,630,488 | $571,970 | $8,628,224 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | UPA Construction Group (AB) Ltd | Generic support building Drumheller Institution, Drumheller, Alberta | $7,446,943 | $1,930,885 | $7,446,942 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Unigertec Inc | Commercial expansion project, Lacolle, Quebec | $4,127,500 | $4,127,500 | $4,127,500 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Valid Manufacturing Ltd | Construction of new transportable cells, Various locations, British Columbia | $5,404,120 | $269,199 | $5,404,120 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Varcon Construction Corp | 50 new bed living units Pittsburgh Institution, Kingston, Ontario | $8,701,571 | $2,313,442 | $8,523,428 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Varcon Construction Corp | Construct new minimum security housing unit at Grand Valley Institution, Kitchener, Ontario | $7,150,591 | $507,783 | $7,150,591 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | W S Morgan Construction Limited | Construction of new medium security housing unit, Gravenhurst, Ontario | $12,302,508 | $83,079 | $12,302,440 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Westpro Infrastructure Ltd | Generic support building Bowden Institution, Innisfail, Alberta | $8,898,776 | $23,565 | $8,898,776 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Westridge Construction Ltd | Detachment construction, Emerald Park, Saskatchewan | $6,452,674 | $0 | $6,452,674 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Wild Stone Engineering Ltd | Detachment demolition and reconstruction, Inuvik, Nunavut | $18,739,183 | $6,000,000 | $6,000,000 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | XL Electric Ltd | Replace transfer switches at Springhill Institution, Springhill, Nova Scotia | $695,692 | $0 | $695,692 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Yellowridge Construction Ltd | Generic support buildings GI/GO at Mission Institution, Mission, British Columbia | $10,372,794 | $0 | $10,372,794 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Yellowridge Sasq'ets Joint Venture | Living unit renovation at Kwìkwèxwelhp Healing Village, Harrison Mills, British Columbia | $4,794,715 | $2,558,252 | $2,558,252 | - |
| 2014/2015 | Public Safety and Emergency Preparedness | Électricité Grimard Inc | Adding lighting in the courtyards, Sainte-Anne-des-Plaines, Quebec | $313,115 | $244,372 | $313,115 | - |
| 2014/2015 | Public Works and Government Services | 9271-3247 Québec Inc | Leasehold improvements of taxes services office, Québec, Quebec | $3,258,367 | $2,791,277 | $3,217,871 | - |
| 2014/2015 | Public Works and Government Services | Atlantic Roofers Limited | Roof remediation for Joseph A Ghiz Building, Summerside, Prince Edward Island | $276,277 | $184,439 | $184,439 | - |
| 2014/2015 | Public Works and Government Services | Avondale Construction Limited | Building modernization Phase 2 - 1st and 3rd floors, Shediac, New Brunswick | $6,027,211 | $3,463,582 | $3,463,582 | - |
| 2014/2015 | Public Works and Government Services | Black & McDonald Limited | Replacement of heat pumps, Moncton, New Brunswick | $2,802,941 | $0 | $2,802,941 | - |
| 2014/2015 | Public Works and Government Services | Construction Cybco Inc | Conversion of storage space into office space and installation of elevators, Montréal, Quebec | $14,959,906 | $4,943,817 | $14,347,079 | - |
| 2014/2015 | Public Works and Government Services | Construction Socam Ltd | Renovation of building envelope and earthquake resistance work, Rigaud, Quebec | $4,523,117 | $80,215 | $4,523,065 | - |
| 2014/2015 | Public Works and Government Services | Construction Socam Ltd | Replacement and installation of burner control valve to existing gas boilers, Montréal, Quebec | $614,582 | $67,447 | $614,582 | - |
| 2014/2015 | Public Works and Government Services | Contracts for other government departments (276) | Contracts awarded and managed by PWGSC on behalf of other government departments | $0 | $168,791,350 | $0 | - |
| 2014/2015 | Public Works and Government Services | Contracts under $250,000 and cost plus contracts under $25,000 (14 contractors) | Total | $0 | $847,896 | $0 | - |
| 2014/2015 | Public Works and Government Services | Contracts under $250,000 and cost plus contracts under $25,000 (5 contractors) | Total | $0 | $42,574 | $0 | - |
| 2014/2015 | Public Works and Government Services | Dover Elevator and Lifts Ltd | Elevator upgrade, Moncton, New Brunswick | $1,507,390 | $11,775 | $1,507,390 | - |
| 2014/2015 | Public Works and Government Services | Dowd Roofing Inc | Roof replacement, Saint John, New Brunswick | $754,209 | $0 | $754,209 | - |
| 2014/2015 | Public Works and Government Services | Green Timbers Limited Partnership (Paid through Computershare Investor Services Inc) | Public-Private Partnership Accommodations Project - RCMP E Division Relocation, Surrey, British-Columbia | $274,036,954 | $1,524,982 | $134,499,705 | - |
| 2014/2015 | Public Works and Government Services | Joneljim Concrete Construction Ltd | Construction for Neville Street Phase 2B electrical building, Reserve Mines, Nova Scotia | $6,100,817 | $5,601,293 | $5,601,293 | - |
| 2014/2015 | Public Works and Government Services | Kone Inc | Elevator upgrade, Saint John, New Brunswick | $519,235 | $289,235 | $519,235 | - |
| 2014/2015 | Public Works and Government Services | Neelco Builders Ltd | Relining of culvert #2 at km 380.7, Alaska Highway, Prophet River, British Columbia | $487,000 | $0 | $487,000 | - |
| 2014/2015 | Public Works and Government Services | Online Constructors Ltd | Bridge culvert #5, Alaska Highway, Various locations, British Columbia | $516,010 | $516,010 | $516,010 | - |
| 2014/2015 | Public Works and Government Services | P S Sidhu Trucking Ltd | Reconstruction of km 555 to 570 of Alaska Highway, Various locations, British Columbia | $10,337,622 | $6,483,015 | $6,483,015 | - |
| 2014/2015 | Public Works and Government Services | Roland Grenier Construction Ltée | Refitting of processing centre, Laval, Quebec | $568,639 | $4,932 | $568,639 | - |
| 2014/2015 | Public Works and Government Services | SNC Lavalin Operations & Maintenance Inc | Betterments to various buildings, Various locations, British Columbia | $5,019,595 | $5,019,595 | $5,019,595 | - |
| 2014/2015 | Public Works and Government Services | SNC Lavalin Operations & Maintenance Inc | Betterments to various buildings, Various locations, New Brunswick, Various Provinces | $2,453,396 | $2,453,396 | $2,453,396 | - |
| 2014/2015 | Public Works and Government Services | SNC Lavalin Operations & Maintenance Inc | Betterments to various buildings, Various locations, Ontario | $5,738,289 | $6,431,864 | $5,738,289 | - |
| 2014/2015 | Public Works and Government Services | St-Denis Thompson Inc | Exterior wall restoration, Moncton, New Brunswick | $6,825,916 | $0 | $6,825,916 | - |
| 2014/2015 | Public Works and Government Services | Teraflex Ltd | Construction of underground conduits that house cablings, Ottawa, Ontario | $985,040 | $71,175 | $985,040 | - |
| 2014/2015 | Public Works and Government Services | The State Group Inc | Burlington Lift Bridge, Hamilton, Ontario | $9,421,016 | $1,326,815 | $1,326,815 | - |
| 2014/2015 | Public Works and Government Services | ThyssenKrupp Elevator (Canada) Limited | Freight and passenger elevator modernization, Thunder Bay, Ontario | $1,058,961 | $0 | $1,058,961 | - |
| 2014/2015 | Transport | 9165-2214 Québec Inc | Replacing the power plant aerodrome Kuujjuaq Airport, Kuujjuaq, Quebec | $4,080,883 | $0 | $4,028,253 | - |
| 2014/2015 | Transport | 9165-2214 Québec Inc | Work on compliance of Transport Canada's storage Tank Systems for Petroleum Products and Allied Petroleum Products, various locations, Quebec | $884,021 | $0 | $884,021 | - |
| 2014/2015 | Transport | BGLA Inc | Upgrade air terminal building at Sept-Îles Airport, Sept-Îles, Quebec | $468,028 | $262,918 | $262,918 | - |
| 2014/2015 | Transport | Bluebird Investments Ltd | Building modifications, Wabush, Newfoundland and Labrador | $1,716,800 | $188,759 | $1,712,702 | - |
| 2014/2015 | Transport | Bouchard et Blanchette Marine Ltée | Natashquan Wharf sheet pile wall rehabilitation, Natashquan, Quebec | $2,142,927 | $1,853,876 | $1,853,876 | - |
| 2014/2015 | Transport | CBCL Ltd | Resurface runway 18/36, Wabush, Newfoundland and Labrador | $725,812 | $47,728 | $202,495 | - |
| 2014/2015 | Transport | Cegertec Experts-Conseils Inc | Havre Saint-Pierre Airport rehabilitation project, Havre Saint-Pierre, Quebec | $336,400 | $292,629 | $292,629 | - |
| 2014/2015 | Transport | Cegertec Experts-Conseils Inc | Schefferville Airport rehabilitation project, Schefferville, Quebec | $389,044 | $44,790 | $337,945 | - |
| 2014/2015 | Transport | Construction Binet | Repair of versatile building - Shefferville Airport, Shefferville, Quebec | $3,369,009 | $0 | $3,369,009 | - |
| 2014/2015 | Transport | Construction Qisaruataq Inc | Developing a turning place at the runway threshold 07-25 - Kuujjuaq Airport, Kuujjuaq, Quebec | $523,403 | $0 | $523,403 | - |
| 2014/2015 | Transport | Contracts under $250,000 and cost plus contracts under $25,000 (137 contractors) | Total | $0 | $9,252,862 | $0 | - |
| 2014/2015 | Transport | Dessau Inc | Replace air terminal power plant at Îles-de-la-Madeleine Airport, Îles-de-la-Madeleine, Quebec | $279,464 | $216,407 | $216,407 | - |
| 2014/2015 | Transport | Expertech Marine Inc | Installation of a cathodic protection at Les Méchins Wharf, Les Méchins, Quebec | $634,375 | $577,218 | $577,218 | - |
| 2014/2015 | Transport | Expertech Marine Inc | Rehabilitate wharf deck and install cathodic protection at Matane Wharf, Matane, Quebec | $388,999 | $238,341 | $338,334 | - |
| 2014/2015 | Transport | Gervais Dubé Inc | Breakwater rehabilitation at Gros-Cacouna port, Gros-Cacouna, Quebec | $3,451,760 | $113,494 | $3,451,760 | - |
| 2014/2015 | Transport | Gil-son Construction Limited | Replace the electrical and mechanical systems at the Digby Ferry Terminal, Digby, Nova Scotia | $825,208 | $176,000 | $176,000 | - |
| 2014/2015 | Transport | Groupe Stavibel Inc/Amiskv/Consortium | Kuujjuaq Airport rehabilitation project, Kuujjuaq, Quebec | $318,071 | $242,118 | $242,118 | - |
| 2014/2015 | Transport | IGLU Construction Inc | Kuujjuaq Airport rehabilitation project, Kuujjuaq, Quebec | $5,248,218 | $4,820,091 | $4,820,091 | - |
| 2014/2015 | Transport | Les Constructions Des Iles Inc | Cap-aux-Meules fisherman's wharf rehabilitation, Îles-de-la-Madeleine, Quebec | $1,227,639 | $215,845 | $694,985 | - |
| 2014/2015 | Transport | Les constructions BLH (1997) Inc | Lighting replacement, Sept-Îles, Quebec | $673,961 | $36,133 | $596,928 | - |
| 2014/2015 | Transport | Les constructions BLH (1997) Inc | Upgrade air terminal building at Sept-Îles Airport, Sept-Îles, Quebec | $793,312 | $698,107 | $698,107 | - |
| 2014/2015 | Transport | Les installations GMR Inc | Work on compliance of Transport Canada's storage Tank Systems for Petroleum Products and Allied Petroleum Products, various locations, Quebec | $1,174,384 | $0 | $1,174,384 | - |
| 2014/2015 | Transport | Les équipements Claude Pednault | Compliance of petroleum and allied petroleum products storage tank systems, various locations, Quebec | $2,154,484 | $0 | $0 | - |
| 2014/2015 | Transport | Modern Construction Ltd | Construction of parking lot holding area for Confederation Bridge, Cape Jourimain, New Brunswick | $607,377 | $607,377 | $607,377 | - |
| 2014/2015 | Transport | NFOE/GRC en Consortium | Upgrade air terminal building at Îles-de-la-Madeleine Airport, Îles-de-la-Madeleine, Quebec | $696,637 | $98,158 | $98,158 | - |
| 2014/2015 | Transport | Neve Refrigeration Inc | Chiller replacement at the Dorval regional office, Dorval, Quebec | $326,003 | $267,080 | $267,080 | - |
| 2014/2015 | Transport | P et B Entreprises Ltée | Surface treatment of runway 07-25, Îles-de-la-Madelaine, Quebec | $383,068 | $333,068 | $383,068 | - |
| 2014/2015 | Transport | PAVEX Ltée | Havre Saint-Pierre Airport rehabilitation project, Havre Saint-Pierre, Quebec | $6,166,835 | $4,735,617 | $4,735,617 | - |
| 2014/2015 | Transport | PAVEX Ltée | Schefferville Airport rehabilitation project, Schefferville, Quebec | $9,741,945 | $849,829 | $849,829 | - |
| 2014/2015 | Transport | PHB Group | St Anthony airport air terminal building expansion, St Anthony, Newfoundland and Labrador | $496,691 | $85,647 | $448,582 | - |
| 2014/2015 | Transport | Peters Bros Construction Ltd | Penticton Airport runway restoration, Penticton, British Columbia | $6,262,037 | $6,262,037 | $6,262,037 | - |
| 2014/2015 | Transport | Progressive Fence Installations Ltd | Port Hardy Airport perimeter fencing replacement, Port Hardy, British Columbia | $405,540 | $405,540 | $405,540 | - |
| 2014/2015 | Transport | Progressive Ventures Construction Ltd | Sandspit Airport perimeter fencing replacement, Sandspit, British Columbia | $300,220 | $300,220 | $300,220 | - |
| 2014/2015 | Transport | Projexco Inc | Replace walkway Cap-aux-Meules Wharf, Îles-de-la-Madeleine, Quebec | $449,879 | $391,284 | $391,284 | - |
| 2014/2015 | Transport | Protec Petroleum Services Ltd | Sandspit Airport fuel tank replacement, Sandspit, British Columbia | $337,382 | $337,382 | $337,382 | - |
| 2014/2015 | Transport | Public Works and Government Services Canada | Penticton Airport runway restoration, Penticton, British Columbia | $766,791 | $463,086 | $766,791 | - |
| 2014/2015 | Transport | Richard Poirier et frères électrique Ltée | Replace air terminal power plant at Îles-de-la-Madeleine Airport, Îles-de-la-Madeleine, Quebec | $1,754,504 | $1,525,987 | $1,525,987 | - |
| 2014/2015 | Transport | SNC-Lavalin Inc | Schefferville Airport rehabilitation project, Schefferville, Quebec | $390,255 | $7,988 | $7,988 | - |
| 2014/2015 | Transport | SNC-Lavalin Operations & Maintenance Inc | Rehabilitate Structures at Pickering Lands Site, Pickering, Ontario | $175,605 | $175,605 | $175,605 | - |
| 2014/2015 | Transport | Sani-Sable LB Inc | Rehabilitate Paspébiac Wharf, Paspébiac, Quebec | $2,670,659 | $2,390,859 | $2,390,859 | - |
| 2014/2015 | Transport | Sani-Sable LB Inc | Site preparation for Mont-Louis Wharf, Saint-Maxime-du-Mont-Louis, Quebec | $3,111,906 | $680,730 | $950,923 | - |
| 2014/2015 | Transport | Seguin Morris | Replace field electrical centre switchgear, Wabush, Newfoundland and Labrador | $400,856 | $100,856 | $400,856 | - |
| 2014/2015 | Transport | Seguin Morris | Replace lighting system 10/28, St Anthony, Newfoundland and Labrador | $484,530 | $20,000 | $484,530 | - |
| 2014/2015 | Transport | The Ontario Construction Company Ltd | Wall Restoration Structure 1 and 1A, Owen Sound, Ontario | $1,415,379 | $9,627 | $1,415,379 | - |
| 2014/2015 | Transport | Traytown Builders Ltd | Air Terminal Building Modifications, St Anthony, Newfoundland and Labrador | $3,558,829 | $2,215,190 | $3,558,829 | - |
| 2014/2015 | Transport | Wendake Construction SEC | La Romaine fisherman's wharf rehabilitation, La Romaine, Quebec | $314,851 | $272,678 | $272,678 | - |
| 2014/2015 | Veterans Affairs | Construction Socam Ltée | Ste-Anne Hospital Modernization project, Sainte-Anne-de-Bellevue, Quebec | $22,162,178 | $0 | $22,162,178 | - |
| 2014/2015 | Veterans Affairs | Contracts under $250,000 and cost plus contracts under $25,000(6 contractors) | Total | $0 | $450,145 | $0 | - |